QWSS to Kollam - Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative - Chlorination arrangements for disinfection purpose at No-2 OHSR, No 3 & 4 OHSR, Paliithottam OHSR and Asramam OHSR under W S Section No-1, Kollam.

Project QWSS to Kollam - Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative - Chlorination arrangements for disinfection purpose at No-2 OHSR, No 3 & 4 OHSR, Paliithottam OHSR and Asramam OHSR under W S Section No-1, Kollam.
Project Code KLMRKI032012078
Type Main project
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description QWSS to Kollam - Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative - Chlorination arrangements for disinfection purpose at No-2 OHSR, No 3 & 4 OHSR, Paliithottam OHSR and Asramam OHSR under W S Section No-1, Kollam.
Status Completed
District Kollam
Executing Office Kollam WS Sn 1
AS Amount (Rs) 1830000
AS Number 6296/AE1(OPERATIONS)/2022/KWA of 2022-2023
TS Amount (Rs) 103800
TS Number TS/2022-2023/2022/20890
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted
Capacity in MLD 0.00
Actual Project Completion Date 31 Oct 2022
Coverage

Packages

No. Project Name Location View
1 QWSS to Kollam - Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative - Chlorination arrangements for disinfection purpose at No-2 OHSR, No 3 & 4 OHSR, Paliithottam OHSR and Asramam OHSR under W S Section No-1, Kollam. Kollam WS Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 May 2023 Final bill submitted to sub division Kollam WS Sn 1 - AE
27 Apr 2023 Final bill submitted to sub division Kollam WS Sn 1 - AE
24 Apr 2023 Final bill submitted to sub division Kollam WS Sn 1 - AE
18 Apr 2023 Final bill submitted to sub division Kollam WS Sn 1 - AE
11 Apr 2023 Final bill submitted to sub division Kollam WS Sn 1 - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 27/08/2022
Scheduled date of Completion of the Project 26 Sep 2022
Expected date of Completion 26/09/2022

Processing Dates

AS Date 03 Mar 2022
TS Date 13 Jun 2022

Other details