| Project | Deposit work - Extension of pipe line in various wards Chithara Grama panchayath phase II |
|---|---|
| Project Code | KLMDEPO112110321 |
| Type | Main project |
| Funding Agency | DEPO |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | Deposit work - Extension of pipe line in various wards Chithara Grama panchayath phase II |
| Status | Completed |
| District | Kollam |
| Executing Office | Madathara Sn |
| AS Amount (Rs) | 4151000 |
| AS Number | C.391/2020 |
| TS Amount (Rs) | 4151000 |
| TS Number | TS/2021-2022/2021/36143 |
| Total Bill Submitted (Rs) | 0 |
| Total Bill Paid (Rs) | 0 |
| Population Benefitted | 10000 |
| Capacity in MLD | 9.70 |
| Actual Project Completion Date | 25 May 2022 |
| Coverage | Partially |
| Implementation Schedule | Download |
| Work Plan | Download |
| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Jun 2022 | 100% completed | Madathara PH Sn - AE | |
| 30 May 2022 | 90% completed | Madathara PH Sn - AE | |
| 26 May 2022 | 85% work completed | Madathara PH Sn - AE | |
| 23 May 2022 | 83% work completed | Madathara PH Sn - AE | |
| 19 May 2022 | 80% work completed | Madathara PH Sn - AE |
| Date of start of Project | 15/03/2022 |
|---|---|
| Scheduled date of Completion of the Project | 03 May 2022 |
| Expected date of Completion | 25/05/2022 |
| AS Date | 18 Nov 2021 |
|---|---|
| TS Date | 04 Dec 2021 |
| Project Officers | View |
|---|