NABARD- RIDF-XXVI- Water Supply and distribution to Melila Panchayath in Kollam District- -Supply,laying,testing and commissioning of distribution networks at Zone V

Project NABARD- RIDF-XXVI- Water Supply and distribution to Melila Panchayath in Kollam District- -Supply,laying,testing and commissioning of distribution networks at Zone V
Project Code KLMNABARD05217436
Type Main project
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme
Description NABARD- RIDF-XXVI- Water Supply and distribution to Melila Panchayath in Kollam District- -Supply,laying,testing and commissioning of distribution networks at Zone V
Status On-going
District Kollam
Executing Office Kollam Project Dn
AS Amount (Rs) 104010000
AS Number GO(Rt)No:280/2021/WRD
TS Amount (Rs) 100550000
TS Number TS/2021-2022/2019/5443
Total Bill Submitted (Rs) 40666679
Total Bill Paid (Rs) 16516231
Population Benefitted 23599
Capacity in MLD 10.30
Actual Project Completion Date 01 Mar 2023
Coverage Zone V area of Melial Panchayath in Kollam District.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 NABARD- RIDF-XXVI- Water Supply and distribution to Melila Panchayath in Kollam District- -Supply,laying,testing and commissioning of distribution networks at Zone V Kollam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Dec 2023 DI and PVC pipe laying completed 86.636 km pipe laid, except pipe laying along NHAI (NH744) Chethady - Padinjjaretheruvu Kollam Project Dn AE
12 Dec 2023 DI and PVC pipe laying completed 86.636 km pipe laid, except pipe laying along NHAI (NH744) Chethady - Padinjjaretheruvu Kollam Project Dn AE
11 Dec 2023 DI and PVC pipe laying completed 86.636 km pipe laid, except pipe laying along NHAI (NH744) Chethady - Padinjjaretheruvu Kollam Project Dn AE
09 Dec 2023 DI and PVC pipe laying completed 86.636 km pipe laid, except pipe laying along NHAI (NH744) Chethady - Padinjjaretheruvu Kollam Project Dn AE
08 Dec 2023 DI and PVC pipe laying completed 86.636 km pipe laid, except pipe laying along NHAI (NH744) Chethady - Padinjjaretheruvu Kollam Project Dn AE

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
15 Nov 2022 Pending Pending Road Cut Related Risk NHAI cutting sanction required No comments available. Pending
15 Nov 2022 Pending Pending Road Cut Related Risk NHAI cutting sanction required No comments available. Pending

Duration & Sanction dates

Date of start of Project 16/08/2021
Scheduled date of Completion of the Project 01 Mar 2023
Expected date of Completion 01/06/2023

Processing Dates

AS Date 07 May 2021
TS Date 21 May 2021

Other details

Project Officers View