NABARD- RIDF-XXVI- Water Supply and distribution to Melila Panchayath in Kollam District- -Supply,laying,testing and commissioning of distribution networks at Zone V
Project |
NABARD- RIDF-XXVI- Water Supply and distribution to Melila Panchayath in Kollam District- -Supply,laying,testing and commissioning of distribution networks at Zone V |
Project Code |
KLMNABARD05217436 |
Type |
Main project |
Funding Agency |
NABARD |
Category |
NABARD |
Type of scheme |
Water Supply |
Scheme |
|
Description |
NABARD- RIDF-XXVI- Water Supply and distribution to Melila Panchayath in Kollam District- -Supply,laying,testing and commissioning of distribution networks at Zone V |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam Project Dn |
AS Amount (Rs) |
104010000
|
AS Number |
GO(Rt)No:280/2021/WRD |
TS Amount (Rs) |
100550000 |
TS Number |
TS/2021-2022/2019/5443 |
Total Bill Submitted (Rs) |
40666679 |
Total Bill Paid (Rs) |
16516231 |
Population Benefitted |
23599 |
Capacity in MLD |
10.30 |
Actual Project Completion Date |
01 Mar 2023 |
Coverage |
Zone V area of Melial Panchayath in Kollam District. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
NABARD- RIDF-XXVI- Water Supply and distribution to Melila Panchayath in Kollam District- -Supply,laying,testing and commissioning of distribution networks at Zone V |
Kollam Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Dec 2023 |
DI and PVC pipe laying completed 86.636 km pipe laid, except pipe laying along NHAI (NH744) Chethady - Padinjjaretheruvu |
Kollam Project Dn AE |
|
12 Dec 2023 |
DI and PVC pipe laying completed 86.636 km pipe laid, except pipe laying along NHAI (NH744) Chethady - Padinjjaretheruvu |
Kollam Project Dn AE |
|
11 Dec 2023 |
DI and PVC pipe laying completed 86.636 km pipe laid, except pipe laying along NHAI (NH744) Chethady - Padinjjaretheruvu |
Kollam Project Dn AE |
|
09 Dec 2023 |
DI and PVC pipe laying completed 86.636 km pipe laid, except pipe laying along NHAI (NH744) Chethady - Padinjjaretheruvu |
Kollam Project Dn AE |
|
08 Dec 2023 |
DI and PVC pipe laying completed 86.636 km pipe laid, except pipe laying along NHAI (NH744) Chethady - Padinjjaretheruvu |
Kollam Project Dn AE |
|
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
15 Nov 2022 |
Pending |
Pending |
Road Cut Related Risk |
NHAI cutting sanction required |
No comments available. |
Pending |
15 Nov 2022 |
Pending |
Pending |
Road Cut Related Risk |
NHAI cutting sanction required |
No comments available. |
Pending |
Duration & Sanction dates
Date of start of Project |
16/08/2021 |
Scheduled date of Completion of the Project |
01 Mar 2023 |
Expected date of Completion |
01/06/2023 |
Processing Dates
AS Date |
07 May 2021 |
TS Date |
21 May 2021 |