- Home
- DEPOSIT-Kilimanoor Panchayath-Pipe line...
DEPOSIT-Kilimanoor Panchayath-Pipe line extension in various wards of Kilimanoor Grama panchayath. -Pipeline Work
Project |
DEPOSIT-Kilimanoor Panchayath-Pipe line extension in various wards of Kilimanoor Grama panchayath. -Pipeline Work |
Project Code |
TVMDEPO032315189 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
DEPOSIT-Kilimanoor Panchayath-Pipe line extension in various wards of Kilimanoor Grama panchayath. -Pipeline Work |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Attingal WS Sn 2 |
AS Amount (Rs) |
1617000
|
AS Number |
400204/DPTP01/GPO/2023/1093/(1) |
TS Amount (Rs) |
1617000 |
TS Number |
WRD/KWA-CE(SR)/EST_TS/14814/2022_26_1_1 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
15 Feb 2024 |
Coverage |
|
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT-Kilimanoor Panchayath-Pipe line extension in various wards of Kilimanoor Grama panchayath. -Pipeline Work |
Attingal WS Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Feb 2024 |
WORK COMPLETED |
Attingal WS Sn no 2 - AE |
|
11 Dec 2023 |
Pipe supplied and work started |
Attingal WS Sn no 2 - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
02 Jan 2024 |
Expected date of Completion |
02/01/2024 |
Processing Dates
AS Date |
06 Mar 2023 |
TS Date |
03 Oct 2023 |