Deposit work - Thariode GP. ARWSS to Padinjarathara and Thariode Villages - providing water connection to Madathuvayal area in Thariode Grama Panchayat

Project Deposit work - Thariode GP. ARWSS to Padinjarathara and Thariode Villages - providing water connection to Madathuvayal area in Thariode Grama Panchayat
Project Code WYDDEPO07218577P1
Type Package
Main Project Deposit work - Thariode GP. ARWSS to Padinjarathara and Thariode Villages - providing water connection to Madathuvayal area in Thariode Grama Panchayat
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work - Thariode GP. ARWSS to Padinjarathara and Thariode Villages - providing water connection to Madathuvayal area in Thariode Grama Panchayat
Status On-going
District Wayanad
Executing Office Kalpetta PH Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 150000
TS Number TS/2021-2022/2021/3701
Technical specification Deposit work - Thariode GP. ARWSS to Padinjarathara and Thariode Villages - providing water connection to Madathuvayal area in Thariode Grama Panchayat
Contractor T . Ismail (Mob: 9496074071)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 28/12/2021
Scheduled date of Completion as per agreement 30 Jun 2022
Expected date of Completion 30/06/2022

Processing Dates

TS Date 03 Aug 2021
Estimate Approval 03 Aug 2021
Tender Closing 24 Sep 2021
Technichal Pre-Qualification 10 Dec 2021
Price bid opening 27 Sep 2021

Approval Dates

Workorder Date 10 Dec 2021
NA 28 Dec 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kalpetta PH Sn 2 - AE
Date: 07/09/2023

Work has been completed | 100% Completed

Bill scrutinizing under Sub division.

Kalpetta PH Sn 2 - AE
Date: 04/09/2023

Work has been completed | 100% Completed