JJM - Setting up of new water treatment lab at JICA WTP Thycattusserry in Alappuzha district
Project |
JJM - Setting up of new water treatment lab at JICA WTP Thycattusserry in Alappuzha district |
Project Code |
ALPJJM09218459 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Others |
Scheme |
4215-01-102-92-02 |
Description |
JJM - Setting up of new water treatment lab at JICA WTP Thycattusserry in Alappuzha district |
Status |
Completed |
District |
Pathanamthitta |
Executing Office |
Alappuzha QC Sn |
AS Amount (Rs) |
5200000
|
AS Number |
GO(Rt) No. 489/2021/WRD |
TS Amount (Rs) |
2000000 |
TS Number |
TS/2021-2022/2021/22412 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
JJM - Setting up of new water treatment lab at JICA WTP Thycattusserry in Alappuzha district |
Alappuzha QC Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
11 Sep 2023 |
Work completed final bill submitted |
Alappuzha QC AE |
|
11 Sep 2023 |
Work completed Final bill submitted |
Alappuzha QC AE |
|
01 Aug 2023 |
Work completed |
Alappuzha QC AE |
|
17 Apr 2023 |
works of chemical area completed.Microbiology area not completed.cc1st and part bill submitted |
Alappuzha QC AE |
|
20 Mar 2023 |
works of chemical area completed.Microbiology area not completed.cc1st and part bill submitted |
Alappuzha QC AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
27/11/2021 |
Scheduled date of Completion of the Project |
11 Jan 2022 |
Expected date of Completion |
Date is not specified |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
27 Oct 2021 |