- Home
- State budget 2021-2022. RWSS to Andoorko...
State budget 2021-2022. RWSS to Andoorkonam- Renovation of Anathazhchira pump house and replace the damaged pipe line with new pipe.
Project |
State budget 2021-2022. RWSS to Andoorkonam- Renovation of Anathazhchira pump house and replace the damaged pipe line with new pipe. |
Project Code |
TVMGOK02229269 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
State budget 2021-2022 RWSS to Andoorkonam- Renovation of Anathazhchira pump house and replace the damaged pipe line with new pipe. |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Attingal WS Dn |
AS Amount (Rs) |
10000000
|
AS Number |
KWA/JB/PIU-1/AEE-1/8/2021-22 |
TS Amount (Rs) |
10000000 |
TS Number |
TS/2021-2022/2021/23422 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
6000 |
Capacity in MLD |
0.40 |
Actual Project Completion Date |
11 Jul 2022 |
Coverage |
part of Andoorkkonam grama panchayath |
Packages
No. |
Project Name |
Location |
View |
1 |
Package duplication |
Attingal WS Sn 2 |
|
2 |
State budget 2021-2022. RWSS to Andoorkonam- Renovation of Anathazhchira pump house and replace the damaged pipe line with new pipe. |
Attingal WS Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
28 Nov 2022 |
Contractor Sri. G. Suresh quoted 15 % above tendered PAC. The quoted amount is greater than the LMR amount. Hence accepted PAC was limited to LMR (ie. 3.3% above tendered PAC). Contractor unwilling to take up the work with this rate. Hence work order cancelled and re tendered. There is no offer received in the second call tender. |
Attingal WS Dn EE |
|
07 Jul 2022 |
Work order issued |
Attingal WS Sn no 2 - AE |
|
14 Mar 2022 |
work tendered |
Attingal WS Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
12/04/2022 |
Scheduled date of Completion of the Project |
11 Jul 2022 |
Expected date of Completion |
31/12/2023 |
Processing Dates
AS Date |
20 Feb 2022 |
TS Date |
03 Mar 2022 |