Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Green Book-CWSS to Harippad and Adjoining Panchayaths-Construction of 14 LL OHSR and connected works at Pallippad

Project Green Book-CWSS to Harippad and Adjoining Panchayaths-Construction of 14 LL OHSR and connected works at Pallippad
Project Code ALPGOK0317484P1
Type Package
Main Project Green Book-CWSS to Harippad and Adjoining Panchayaths-Phase II-Construction of 14 LL OHSR and connected works at Pallippad and laying 9km raw water pumping main from intake at Mullasery kadavu to WTP at Pallipad
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Construction 14 LL OHSR at Pallippad WTP site for CWSS to Harippad and adjoining panchayaths for distribution of drinking water at Pallippad Panchayath area.
Status Short Closed
District Alappuzha
Executing Office Alappuzha Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 45000000
TS Number TS/2017-2018/2017/4782
Technical specification Construction 14 LL OHSR at Pallippad WTP site for CWSS to Harippad and adjoining panchayaths for distribution of drinking water at Pallippad Panchayath area.
Contractor M/s Chicago constructions International pvt ltd (Mob: 9447770536)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 23/11/2018
Scheduled date of Completion as per agreement 30 Nov 2019
Expected date of Completion 30/06/2020

Processing Dates

TS Date 24 Mar 2018
Estimate Approval 24 Mar 2018
NIT Approval 02 Apr 2018
Supplying and Laying 02 Apr 2018
Tender Closing 23 Apr 2018
Technichal Pre-Qualification 11 May 2018
Price bid opening 15 May 2018

Approval Dates

CE Approval 21 Jun 2018
Head Office Approval 21 Jun 2018
Board Approval 21 Jun 2018
Final Approval 21 Jun 2018
Workorder Date 04 Jul 2018
NA 18 Jul 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha Project Dn AE4
Date: 18/03/2021

Work has been completed | 100% Completed

Work Completion certificate issued. CC III and Final bill payment pending.