Project | Green Book-CWSS to Harippad and Adjoining Panchayaths-Construction of 14 LL OHSR and connected works at Pallippad |
---|---|
Project Code | ALPGOK0317484P1 |
Type | Package |
Main Project | Green Book-CWSS to Harippad and Adjoining Panchayaths-Phase II-Construction of 14 LL OHSR and connected works at Pallippad and laying 9km raw water pumping main from intake at Mullasery kadavu to WTP at Pallipad |
Funding Agency | GOK |
Category | State plan |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | Construction 14 LL OHSR at Pallippad WTP site for CWSS to Harippad and adjoining panchayaths for distribution of drinking water at Pallippad Panchayath area. |
Status | Short Closed |
District | Alappuzha |
Executing Office | Alappuzha Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 45000000 |
TS Number | TS/2017-2018/2017/4782 |
Technical specification | Construction 14 LL OHSR at Pallippad WTP site for CWSS to Harippad and adjoining panchayaths for distribution of drinking water at Pallippad Panchayath area. |
Contractor | M/s Chicago constructions International pvt ltd (Mob: 9447770536) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 23/11/2018 |
---|---|
Scheduled date of Completion as per agreement | 30 Nov 2019 |
Expected date of Completion | 30/06/2020 |
TS Date | 24 Mar 2018 |
---|---|
Estimate Approval | 24 Mar 2018 |
NIT Approval | 02 Apr 2018 |
Supplying and Laying | 02 Apr 2018 |
Tender Closing | 23 Apr 2018 |
Technichal Pre-Qualification | 11 May 2018 |
Price bid opening | 15 May 2018 |
CE Approval | 21 Jun 2018 |
---|---|
Head Office Approval | 21 Jun 2018 |
Board Approval | 21 Jun 2018 |
Final Approval | 21 Jun 2018 |
Workorder Date | 04 Jul 2018 |
NA | 18 Jul 2018 |
Alappuzha Project Dn AE4 |
Date: 18/03/2021 |
Work has been completed | 100% Completed
Work Completion certificate issued. CC III and Final bill payment pending.