Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Deposit Work-Muthukulam Block Panchayat-Project No.22/23-Supplying Submersible pump sets as spare pump sets in various schemes of PH Section Kayamkulam Under Muthukulam block panchayat

Project Deposit Work-Muthukulam Block Panchayat-Project No.22/23-Supplying Submersible pump sets as spare pump sets in various schemes of PH Section Kayamkulam Under Muthukulam block panchayat
Project Code ALPDEPO112213954
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit Work-Muthukulam Block Panchayat-Project No.22/23-Supplying Submersible pump sets as spare pump sets in various schemes of PH Section Kayamkulam Under Muthukulam block panchayat
Status Completed
District Alappuzha
Executing Office Kayamkulam PH Sn
AS Amount (Rs) 1093000
AS Number D-60/2022
TS Amount (Rs) 1060000
TS Number WRD/KWA-CE(CR)/EST_TS/13378/2022_26_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date 24 Aug 2023
Coverage

Packages

No. Project Name Location View
1 Deposit Work-Muthukulam Block Panchayat-Project No.22/23-Supplying Submersible pump sets as spare pump sets in various schemes of PH Section Kayamkulam Under Muthukulam block panchayat Kayamkulam PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Feb 2024 work completed on 24.08.2023 Kayamkulam AE
06 Feb 2024 Work tendered. Due to some technical problems in accepting tenders tender cancelled. re tendered Kayamkulam AE
01 Jan 2024 Work tendered. Due to some technical problems in accepting tenders tender cancelled. re tendered Kayamkulam AE
16 Nov 2023 Work tendered. Due to some technical problems in accepting tenders tender cancelled. re tendered Kayamkulam AE
10 Nov 2023 Work tendered. Due to some technical problems in accepting tenders tender cancelled. re tendered Kayamkulam AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 17/04/2023
Scheduled date of Completion of the Project 01 May 2023
Expected date of Completion 01/05/2023

Processing Dates

AS Date 14 Nov 2022
TS Date 17 Jan 2023

Other details

Project Officers View