- Jal Jeevan Mission - 2020-21- PHASE III...
Jal Jeevan Mission - 2020-21- PHASE III -Supplying, Laying testing commissioning and maintenance of 250 mm DI K9, Pumping main from Sasthanagar to OHSR Near N.S.S Eng. College by replacing 160 mm PVC pumping Main and Providing of FHTCs(800 Nos-with PE Pipe) in Akathethara Grama Panchayath
Project |
Jal Jeevan Mission - 2020-21- PHASE III -Supplying, Laying testing commissioning and maintenance of 250 mm DI K9, Pumping main from Sasthanagar to OHSR Near N.S.S Eng. College by replacing 160 mm PVC pumping Main and Providing of FHTCs(800 Nos-with PE Pipe) in Akathethara Grama Panchayath |
Project Code |
PKDJJM022212292 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission - 2020-21- PHASE III -Supplying, Laying testing commissioning and maintenance of 250 mm DI K9, Pumping main from Sasthanagar to OHSR Near N.S.S Eng. College by replacing 160 mm PVC pumping Main and Providing of FHTCs(800 Nos-with PE Pipe) in Akathethara Grama Panchayath |
Status |
On-going |
District |
Palakkad |
Executing Office |
Malampuzha Sn |
AS Amount (Rs) |
37000000
|
AS Number |
489/2021/WRD |
TS Amount (Rs) |
35500000 |
TS Number |
TS/2021-2022/2021/37527 |
Total Bill Submitted (Rs) |
17048391 |
Total Bill Paid (Rs) |
17048391 |
Population Benefitted |
3000 |
Capacity in MLD |
12.50 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Akathethara Grama Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission - 2020-21- PHASE III -Supplying, Laying testing commissioning and maintenance of 250 mm DI K9, Pumping main from Sasthanagar to OHSR Near N.S.S Eng. College by replacing 160 mm PVC pumping Main and Providing of FHTCs(800 Nos-with PE Pipe) in Akathethara Grama Panchayath |
Malampuzha Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
29 Mar 2023 |
Work completed |
Malampuzha Sn AE |
|
09 Mar 2023 |
Work completed |
Malampuzha Sn AE |
|
08 Feb 2023 |
Work completed |
Malampuzha Sn AE |
|
02 Feb 2023 |
Work completed |
Malampuzha Sn AE |
|
27 Jan 2023 |
Work Completed |
Malampuzha Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
17/12/2021 |
Scheduled date of Completion of the Project |
16 Apr 2022 |
Expected date of Completion |
30/09/2022 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
30 Nov 2021 |