KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package II
| Project |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package II |
| Project Code |
ALPKIIFB0919495P2 |
| Type |
Package |
| Main Project |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality
|
| Funding Agency |
KIIFB |
| Category |
KIIFB WATER SUPPLY SCHEME |
| Type of scheme |
Water Supply |
| Scheme |
KIIFB |
| Description |
Supplying and laying CWPM from Sump (S1) at WTP to OHSR(R1) at Malayil-400mm DI K9-2250m, Construction of 15LL capacity OHSR (R1) at Malayil,Supplying and laying distribution line at Chengannoor municipality Zone 1 t0 4-152km, Railway push through work at RUB Chengannoor |
| Status |
On-going |
| District |
Alappuzha |
| Executing Office |
KIIFB Projects (ALP) |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
630540000 |
| TS Number |
TS/2020-2021/2020/26214 |
| Technical specification |
CWPM from Sump (S1) at WTP to OHSR(R1) at Malayil-400mm DI K9-2250m
Construction of 15LL capacity OHSR (R1) at Malayil
Supplying and laying distribution line at Chengannoor municipality Zone 1 t0 4-190km
Railway push through work at RUB Chengannoor |
| Contractor |
M/s SURYA INTERNATIONAL ENTERPRISE PVT LTD (Mob: 9439525334) |
No project review have been added to this project
Reported Issues
| Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
| 10 Jan 2022 |
Pending |
24 Jan 2022 |
Contract Related Risks |
Construction of 15 LL OHSR at Malayil, Chengannur Municipality not started |
No comments added. |
Action Taken |
| 01 Oct 2021 |
Pending |
Pending |
Road Cut Related Risk |
Road cutting permission from KSTP is required for laying pipe in MC road. The road is under DLP |
No comments available. |
Pending |
| 01 Oct 2021 |
Pending |
Pending |
Road Cut Related Risk |
Delay in laying pipes in PWD roads |
No comments available. |
Pending |
| 01 Sep 2021 |
Pending |
24 Sep 2021 |
Approval/Permissions Related (from other departments excluding road cut permission and land related) |
Permission from railway is required for Pipeline crossing at km 92/800-900 between Thiruvalla and Chengannoor stations. |
No comments added. |
Action Taken |
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
02/07/2021 |
| Scheduled date of Completion as per agreement |
01 Jan 2023 |
| Expected date of Completion |
31/12/2025 |
Processing Dates
| TS Date |
22 Nov 2020 |
| Estimate Approval |
21 Nov 2020 |
| NIT Approval |
25 Nov 2020 |
| Tender Closing |
10 Feb 2021 |
| Technichal Pre-Qualification |
17 Feb 2021 |
| Price bid opening |
27 Feb 2021 |
Approval Dates
| Workorder Date |
04 May 2021 |
| NA |
02 Jul 2021 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Alappuzha KIIFB - AE 1 |
| Date: 02/07/2026 |
Work in progress | 45% Completed
Agmt no: 02/2021-22/SE/PHC/ALP Dt: 02/07/2021. Original TOC 01.01.2023. TOC extended to 30.06.2024. Malayil OHSR- Concreting of side wall of the tank completed. Steel work of tank cover slab is in progress. Kodiyettukara railway under passage 400/250mm MS Pipe laying completed. Valve chamber completed. Valve fitting progressing. Pipe laying- 90mm PVC pipe -7251m,110mm PVC pipe -11821m and 160mm PVC pipe- 14391m, 250 mm DI Pipe- 444m , 200mm DI Pipe- 446m, 400mm DI Pipe- 755.30m laid(Pumping main from WTP to Malayil OHSR). (Total laid length=35108.30m)..
| Alappuzha KIIFB - AE 1 |
| Date: 29/06/2026 |
Work in progress | 45% Completed
Agmt no: 02/2021-22/SE/PHC/ALP Dt: 02/07/2021. Original TOC 01.01.2023. TOC extended to 30.06.2024. Malayil OHSR- Concreting of side wall of the tank completed. Steel work of tank cover slab is in progress. Kodiyettukara railway under passage 400/250mm MS Pipe laying completed. Valve chamber completed. Valve fitting progressing. Pipe laying- 90mm PVC pipe -7251m,110mm PVC pipe -11821m and 160mm PVC pipe- 14391m, 250 mm DI Pipe- 444m , 200mm DI Pipe- 446m, 400mm DI Pipe- 755.30m laid(Pumping main from WTP to Malayil OHSR). (Total laid length=35108.30m)..