Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Deposit - Supply and Erection of Water Treatment Plant Reverse osmosis System capable of Treating of Row Water having put capacity of 1250 litre/hr, the treated Water will confirm to IS drinking Water standard IS 10500/1991 and Packaged Drinking water Standard IS 14543-Near EK Nayanar library in Ambalapuzha South Panchayath

Project Deposit - Supply and Erection of Water Treatment Plant Reverse osmosis System capable of Treating of Row Water having put capacity of 1250 litre/hr, the treated Water will confirm to IS drinking Water standard IS 10500/1991 and Packaged Drinking water Standard IS 14543-Near EK Nayanar library in Ambalapuzha South Panchayath
Project Code ALPDEPO112215351
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit - Supply and Erection of Water Treatment Plant Reverse osmosis System capable of Treating of Row Water having put capacity of 1250 litre/hr, the treated Water will confirm to IS drinking Water standard IS 10500/1991 and Packaged Drinking water Standard IS 14543-Near EK Nayanar library in Ambalapuzha South Panchayath
Status On-going
District Alappuzha
Executing Office Alappuzha PH Sn
AS Amount (Rs) 709713
AS Number KWA/JB/HO/Sn(O)/1/215/2016
TS Amount (Rs) 709713
TS Number WRD/KWA-CE(CR)EST_TS/3361/2023_5_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
No Packages has been added for this project.

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Jan 2024 R.O Plant Supplied Alappuzha PH Sn AE
24 Jan 2024 R.O Plant Suppled Alappuzha PH Sn AE
01 Jan 2024 Temporary Shelter and Tube Well under Construction by Panchayath Authority. Alappuzha PH Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 28/10/2023
Scheduled date of Completion of the Project 26 Nov 2023
Expected date of Completion 31/01/2024

Processing Dates

AS Date 01 Nov 2022
TS Date 07 Aug 2023

Other details

Project Officers View