Deposit Work 2021-22 - DesamangalamGramaPanchayat - (Project No. 102/2021) - RWSS to Desamangalam - Supply, erection, testing and commissioning of 40 HP Vertical Turbine Motor pumpset at Pallam Pump house
Project |
Deposit Work 2021-22 - DesamangalamGramaPanchayat - (Project No. 102/2021) - RWSS to Desamangalam - Supply, erection, testing and commissioning of 40 HP Vertical Turbine Motor pumpset at Pallam Pump house |
Project Code |
TCRDEPO092110429 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit Work 2021-22 - DesamangalamGramaPanchayat - (Project No. 102/2021) - RWSS to Desamangalam - Supply, erection, testing and commissioning of 40 HP Vertical Turbine Motor pumpset at Pallam Pump house |
Status |
Short Closed |
District |
Thrissur |
Executing Office |
Vadakanchery PH Sub Dn |
AS Amount (Rs) |
1200000
|
AS Number |
A202/2021 |
TS Amount (Rs) |
1200000 |
TS Number |
TS/2022-23/2021/10713 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
2000 |
Capacity in MLD |
0.70 |
Actual Project Completion Date |
Date is not specified |
Coverage |
PALLAM |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit Work 2021-22 - DesamangalamGramaPanchayat - (Project No. 102/2021) - RWSS to Desamangalam - Supply, erection, testing and commissioning of 40 HP Vertical Turbine Motor pumpset at Pallam Pump house |
Vadakanchery PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
03 Jan 2023 |
Short Closed. |
Wadakkanchery PH Sub Dn - AEE |
|
31 Dec 2022 |
tender opened 31/10/2022, still nobody quoted this work |
Vadakkanchery PH Sn |
|
26 Dec 2022 |
tender opened 31/10/2022, still nobody quoted this work |
Vadakkanchery PH Sn |
|
24 Dec 2022 |
tender opened 31/10/2022, still nobody quoted this work |
Vadakkanchery PH Sn |
|
21 Dec 2022 |
tender opened 31/10/2022, still nobody quoted this work |
Vadakkanchery PH Sn |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
23/08/2022 |
Scheduled date of Completion of the Project |
30 Sep 2022 |
Expected date of Completion |
30/09/2022 |
Processing Dates
AS Date |
08 Sep 2021 |
TS Date |
09 May 2022 |