Deposit work of Thiruvanathapuram corporation - Project No-S0548/22-Improving water supply by laying 110mm pvc Pipe line at Subramanyam lane in Vazhuthakadu ward.
Project |
Deposit work of Thiruvanathapuram corporation - Project No-S0548/22-Improving water supply by laying 110mm pvc Pipe line at Subramanyam lane in Vazhuthakadu ward. |
Project Code |
TVMDEPO062212251 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work of Thiruvanathapuram corporation - Project No-S0548/22-Improving water supply by laying 110mm pvc Pipe line at Subramanyam lane in Vazhuthakadu ward. |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Palayam Sn(Maintenance) |
AS Amount (Rs) |
954000
|
AS Number |
J4/548/21 |
TS Amount (Rs) |
954000 |
TS Number |
7096/2022-23 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
80 |
Capacity in MLD |
0.02 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Improving water supply to Subramanyam lane by laying 110mm pvc main and alteration of 15 service lines |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work of Thiruvanathapuram corporation - Project No-S0548/22-Improving water supply by laying 110mm pvc Pipe line at Subramanyam lane in Vazhuthakadu ward. |
Palayam Sn(Maintenance) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
16 May 2023 |
Work completed, bill preparation ongoing |
Palayam Sn AE |
|
11 May 2023 |
tile relaying ongoing |
Palayam Sn AE |
|
04 May 2023 |
Restoration pending |
Palayam Sn AE |
|
27 Apr 2023 |
Road restoration completed |
Palayam Sn AE |
|
08 Apr 2023 |
Main pipe laying work ongoing |
Palayam Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
09 Nov 2022 |
Expected date of Completion |
09/11/2022 |
Processing Dates
AS Date |
08 Jun 2022 |
TS Date |
14 Jun 2022 |