Jal Jeevan Mission (JJM)-Jal Jeevan Mission - 2021-22 - Phase II(Balance work) - Velloor panchayath --Providing FHTC in Various wards by Rectrofitting /Augumenting/Extending the existing Distribution system coming under the jurisdiction of P.H. Division Kaduthuruthy-Pipeline Work

Project Jal Jeevan Mission (JJM)-Jal Jeevan Mission - 2021-22 - Phase II(Balance work) - Velloor panchayath --Providing FHTC in Various wards by Rectrofitting /Augumenting/Extending the existing Distribution system coming under the jurisdiction of P.H. Division Kaduthuruthy-Pipeline Work
Project Code KTMJJM122014305
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Jal Jeevan Mission - 2021-22 - Phase II(Balance work) - Velloor panchayath --Providing FHTC in Various wards by Rectrofitting /Augumenting/Extending the existing Distribution system coming under the jurisdiction of P.H. Division Kaduthuruthy-Pipeline Work
Status On-going
District Kottayam
Executing Office Kaduthuruthy PH Sub Dn
AS Amount (Rs) 117000000
AS Number GO(Rt) No 777/2020/WRD
TS Amount (Rs) 16050000
TS Number WRD/KWA-CE(SR)/EST_TS/1001/2022_26_1_1
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 150
Capacity in MLD 45.00
Actual Project Completion Date 21 Sep 2023
Coverage Chemmanchi area in ward 2 of Velloor panchayath is facing acute shortage of drinking water, as this elevated area cannot be fed from the existing scheme. The capacity of the existing GLSR is quite insufficient to meet the present requirement. Hence an OHSR of capacity 1 LL is proposed along with a stand bye pumpset at WTP Mevalloor.The land required for the GLSR is to be made available.

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-Jal Jeevan Mission - 2021-22 - Phase II(Balance work) - Velloor panchayath --Providing FHTC in Various wards by Rectrofitting /Augumenting/Extending the existing Distribution system coming under the jurisdiction of P.H. Division Kaduthuruthy-Pipeline Work Peruva Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 May 2024 No work Kaduthuruthy Dn EE
15 May 2024 No work Kaduthuruthy Dn EE
14 May 2024 No work Kaduthuruthy Dn EE
13 May 2024 No work Kaduthuruthy Dn EE
12 May 2024 No work Kaduthuruthy Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/04/2023
Scheduled date of Completion of the Project 21 Sep 2023
Expected date of Completion 21/09/2023

Processing Dates

AS Date 24 Dec 2022
TS Date 20 Jan 2023