Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

State Plan 2021-22 - TSS - Supply, installation, testing & commissioning of one number additional 250 kVA Diesel Generator set incomer feeder of 400 A rating in the existing main panel installed at Sewage pump house, Kuriathy, Thiruvananthapuram

Project State Plan 2021-22 - TSS - Supply, installation, testing & commissioning of one number additional 250 kVA Diesel Generator set incomer feeder of 400 A rating in the existing main panel installed at Sewage pump house, Kuriathy, Thiruvananthapuram
Project Code TVMGOK08217886
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State Plan 2021-22 - TSS - Supply, installation, testing & commissioning of one number additional 250 kVA Diesel Generator set incomer feeder of 400 A rating in the existing main panel installed at Sewage pump house, Kuriathy, Thiruvananthapuram
Status Completed
District Thiruvananthapuram
Executing Office Kuriathy Sewerage Sn 3
AS Amount (Rs) 600000
AS Number KWA/JB/PIU1/AE1/12/2021
TS Amount (Rs) 510940
TS Number TS/2021-2022/2021/10393
Total Bill Submitted (Rs) 510940
Total Bill Paid (Rs) 0
Population Benefitted 10000
Capacity in MLD 0.00
Actual Project Completion Date 27 Oct 2021
Coverage Providing generator facility at Kuriathy pump house
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 State Plan 2021-22 - TSS - Supply, installation, testing & commissioning of one number additional 250 kVA Diesel Generator set incomer feeder of 400 A rating in the existing main panel installed at Sewage pump house, Kuriathy, Thiruvananthapuram Kuriathy Sewerage Sn 3

Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Oct 2021 Work completed Pattoor Sewerage Dn
27 Oct 2021 Work completed. Kuriyathy Sew Sn 3 AE
22 Oct 2021 Work in progress 50% completed Pattoor Sewerage Dn
18 Oct 2021 Work in progress 50% completed Kuriathy Sew Sub Dn AEE
13 Oct 2021 Work in progress 50% completed Kuriathy Sew Sub Dn AEE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 06/09/2021
Scheduled date of Completion of the Project 05 Nov 2021
Expected date of Completion 05/11/2021

Processing Dates

AS Date 02 Aug 2021
TS Date 03 Aug 2021

Other details

Project Officers View