Project | DEPOSIT - KWA Utility Shifiting (2022-23) - CWSS to Pulpally and Mullankolly - Replacement of Distribution line from Kappiset Jn to Thazhe Chettappalam and Gravity Main from Thannitheru to Pulpally along the Payampally - Kappiset PWD Road |
---|---|
Project Code | WYDDEPO092212996P1 |
Type | Package |
Main Project | DEPOSIT - KWA Utility Shifiting (2022-23) - CWSS to Pulpally and Mullankolly - Replacement of Distribution line from Kappiset Jn to Thazhe Chettappalam and Gravity Main from Thannitheru to Pulpally along the Payampally - Kappiset PWD Road |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | PWD Deposit - CWSS to Pulpally and Mullankolly - Replacement of Distribution line and Gravity Main along the Payampally - Kappiset PWD Road |
Status | On-going |
District | Wayanad |
Executing Office | Sulthan Bathery Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 2600000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/6043/2022_26_1_1 |
Technical specification | Replacement of Distribution line and Gravity Main along the Payampally - Kappiset PWD Road |
Contractor | Ashraf.K.V (Mob: 7034458683) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 01/12/2022 |
---|---|
Scheduled date of Completion as per agreement | 31 May 2023 |
Expected date of Completion | 31/05/2023 |
TS Date | 17 Oct 2022 |
---|---|
Estimate Approval | 17 Oct 2022 |
NIT Approval | 17 Oct 2022 |
Tender Closing | 27 Oct 2022 |
Technichal Pre-Qualification | 27 Oct 2022 |
Price bid opening | 29 Oct 2022 |
Workorder Date | 22 Nov 2022 |
---|---|
NA | 01 Dec 2022 |
Sulthan Bathery PH Sn - AE |
Date: 24/02/2023 |
Work has been completed | 100% Completed
Pipe laying work completed..
Sulthan Bathery PH Sn - AE |
Date: 21/02/2023 |
Work in progress | 56% Completed
Pipe laying work on progress.