State Plan Optimisation of Production and Transmission - CWSS to Vandazhi, Kizhakkenchery, Vadakkenchery and Kannambra Panchayaths in Alathur Taluk- Phase- I- Design, Construction, trial running commissioning and maintenance 24.5 MLD Water Treatment Plant & 24.50 LL OHSR, Construction of Substation, Supplying , laying, testing, commissioning and maintenance of Clear Water Pumping Main, Design, supply, erection, commissioning and maintenance of Clear Water pump sets & transformer etc– Phase I - Part I

Project State Plan Optimisation of Production and Transmission - CWSS to Vandazhi, Kizhakkenchery, Vadakkenchery and Kannambra Panchayaths in Alathur Taluk- Phase- I- Design, Construction, trial running commissioning and maintenance 24.5 MLD Water Treatment Plant & 24.50 LL OHSR, Construction of Substation, Supplying , laying, testing, commissioning and maintenance of Clear Water Pumping Main, Design, supply, erection, commissioning and maintenance of Clear Water pump sets & transformer etc– Phase I - Part I
Project Code PKDGOI0918625
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Design, construction, trial running, commissioning and maintenance of 24.5 MLD water treatment plant & 24.50 LL OHSR, construction of substation, supplying laying testing commissioning of clear water pumping main, design, supply, erection, commissioning and maintenance of clear water pumpsets & transformer
Status On-going
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 179500000
AS Number KWA/JB/P&M/2/331/2014
TS Amount (Rs) 179500000
TS Number CE/NR/17/2016-2017
Total Bill Submitted (Rs) 111250848
Total Bill Paid (Rs) 111250848
Population Benefitted 174254
Capacity in MLD 24.50
Actual Project Completion Date Date is not specified
Coverage 100 lpcd in Vandazhy, Kizhakkencherry , Vadakkencherry and Kannambra Panchayaths
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 State Plan Optimisation of Production and Transmission - CWSS to Vandazhi, Kizhakkenchery, Vadakkenchery and Kannambra Panchayaths in Alathur Taluk- Phase- I- Design, Construction, trial running commissioning and maintenance 24.5 MLD Water Treatment Plant & 24.50 LL OHSR, Construction of Substation, Supplying , laying, testing, commissioning and maintenance of Clear Water Pumping Main, Design, supply, erection, commissioning and maintenance of Clear Water pump sets & transformer etc– Phase I - Part I Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Dec 2023 Work in progress | 83% Completed | 01/12/2023 OHSR -Plastering work and staircase reinforcement work in progress 1) Raw water channel side wall concreting work complete 2) Purification channel bottom slab concreting work completed 3) chemical house plastering work is in progress 4) Clarifloculator. Driven bridge installation work, Block work of pump house in progress, 5) OHSR-cover slab concreting work completed 6). OHSR- pipe gallery control chamber concrete work complete, Distribution pipe erecting work in progress 7).Clarifier no.1 and 2 outside plastering work in progress 8) Aerator Forth tray concreting work is in progress 9) B filter house, –Plastering work in progres Chittur Project Dn - AE 3
03 Nov 2023 Work in progress | 83% Completed | 03/11/2023OHSR -Plastering work in progress 1) Raw water channel side wall concreting work complete 2) Purification channel bottom slab concreting work completed 3) chemical house plastering work is in progress 4) Clarifloculator. Driven bridge installation work, Block work of pump house in progress, 5) OHSR-cover slab concreting work completed 6). OHSR- pipe gallery control chamber concrete work complete, Distribution pipe erecting work in progress 7).Clarifier no.1 and 2 outside plastering work in progress 8) Aerator Forth tray concreting work is in progress 9) B filter house, –Plastering work in progress Chittur Project Dn - AE 3
12 Oct 2023 Work in progress | 83% Completed | 12/10/2023 OHSR -Plastering work in progress 1) Raw water channel side wall concreting work complete 2) Purification channel bottom slab concreting work completed 3) chemical house plastering work is in progress 4) Clarifloculator. Driven bridge installation work, Block work of pump house in progress, 5) OHSR-cover slab concreting work completed 6). OHSR- pipe gallery control chamber concrete work complete, Distribution pipe erecting work in progress 7).Clarifier no.1 and 2 outside plastering work in progress 8) Aerator Forth tray concreting work is in progress 9) B filter house, –Plastering work in progress Chittur Project Dn - AE 3
07 Sep 2023 Work in progress | 83% Completed | 07/09/2023 OHSR -Plastering work in progress 1) Raw water channel side wall concreting work complete 2) Purification channel bottom slab concreting work completed 3) chemical house plastering work is in progress 4) Clarifloculator. Driven bridge installation work, Block work of pump house in progress, 5) OHSR-cover slab concreting work completed 6). OHSR- pipe gallery control chamber concrete work complete, Distribution pipe erecting work in progress 7).Clarifier no.1 and 2 outside plastering work in progress 8) Aerator Forth tray concreting work is in progress 9) B filter house, –Plastering work in progress Chittur Project Dn - AE 3
04 Aug 2023 Work in progress | 83% Completed | 04/08/2023 OHSR -Plastering work in progress 1) Raw water channel side wall concreting work complete 2) Purification channel bottom slab concreting work completed 3) chemical house plastering work is in progress 4) Clarifloculator. Driven bridge installation work, Block work of pump house in progress, 5) OHSR-cover slab concreting work completed 6). OHSR- pipe gallery control chamber concrete work complete, Distribution pipe erecting work in progress 7).Clarifier no.1 and 2 outside plastering work in progress 8) Aerator Forth tray concreting work is in progress 9) B filter house, –Plastering work in progress Chittur Project Dn - AE 3

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 19/08/2017
Scheduled date of Completion of the Project 22 May 2019
Expected date of Completion 31/12/2023

Processing Dates

AS Date 18 Oct 2014
TS Date 01 Aug 2016

Other details

Project Officers View