Project | JJM- Innovation/R&D/ Sensor based real time monitoring system in Kuruppampady, Karippelipady, Nellimolam & Keezhillam Pump Houses under Kuruppampady section |
---|---|
Project Code | EKMJJM09218367P3 |
Type | Package |
Main Project | JJM (2021-22) - Innovation/ GSM based real time monitoring system under JJM support activities- Automation of various pump houses under PH Division, Aluva |
Funding Agency | JJM |
Category | JJM - Automation |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM- Innovation/R&D/ Sensor based real time monitoring system in Kuruppampady, Karippelipady, Nellimolam & Keezhillam Pump Houses under Kuruppampady section |
Status | On-going |
District | Ernakulam |
Executing Office | Kuruppampady Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 269900 |
TS Number | TS/2021-2022/2021/39190 Dated: 23-11-2021 |
Technical specification | Sensor based real time monitoring system |
Contractor | SH Infranet Management Solutions LLP (Mob: 9207059333) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 20/12/2021 |
---|---|
Scheduled date of Completion as per agreement | 28 Dec 2021 |
Expected date of Completion | 20/01/2022 |
TS Date | 23 Nov 2021 |
---|---|
Estimate Approval | 23 Nov 2021 |
NIT Approval | 22 Dec 2021 |
Tender Closing | 21 Dec 2021 |
Technichal Pre-Qualification | 21 Dec 2021 |
Price bid opening | 21 Dec 2021 |
Workorder Date | 23 Dec 2021 |
---|---|
NA | 20 Dec 2021 |
Kuruppampady AE |
Date: 21/02/2022 |
Work has been completed | 100% Completed
7 days trial run completed . Work completed .
Kuruppampady AE |
Date: 19/02/2022 |
Work in progress | 98% Completed
Trial run started.