Amrut-2016-17- Strengthening the existing distribution system in Thrissur corporation area ( Phase II). Replacement of 80/100/125/200/300mm AC pipes by supplying, laying ,Testing and commissioning 160mm PVC pipes and 200/300/350mm DI k9 pipes at various places in Thrissur corporation- 12.95CR
Project |
Amrut-2016-17- Strengthening the existing distribution system in Thrissur corporation area ( Phase II). Replacement of 80/100/125/200/300mm AC pipes by supplying, laying ,Testing and commissioning 160mm PVC pipes and 200/300/350mm DI k9 pipes at various places in Thrissur corporation- 12.95CR |
Project Code |
TCRAMRUT11171086 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
1)350 MM DI K9-1020 M
2) 300 MM DI K9-1234 M
3) 250 MM DI K9-1288 M
4)200 mmDI K9-816 M
5)160 mm PVC-33000 M |
Status |
Completed |
District |
Thrissur |
Executing Office |
Thrissur PH Dn |
AS Amount (Rs) |
129500000
|
AS Number |
GO(Rt) No.3530/2017/LSGD |
TS Amount (Rs) |
129500000 |
TS Number |
TS/CE/KWA/52/17-18 |
Total Bill Submitted (Rs) |
103236292 |
Total Bill Paid (Rs) |
103236292 |
Population Benefitted |
12000 |
Capacity in MLD |
36.00 |
Actual Project Completion Date |
24 Sep 2021 |
Coverage |
Thrissur corporation
25/09/2021 Commissioned |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Amruth - Strengthening the existing distribution system in Thrissur( 12.95 Cr.) corporation area ( Phase II). Replacement of 80/100/125/200/300mm AC pipes by supplying, laying ,Testing and commissioning 160mm PVC pipes and 200/300/350mm DI k9 pipes at various places in Thrissur corporation |
Thrissur WW Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
18 Jan 2023 |
Final bill submitted to Thrissur Corporation on 11/01/2023. |
Thrissur PH Dn EE |
|
28 Jan 2022 |
Work Completed |
Thrissur PH Dn EE |
|
22 Sep 2021 |
connection shifting work at ollukkara mukkattukara road and Mannuthy paravattany road is in progress |
Thrissur WW Sn - AE 2 |
|
13 Sep 2021 |
INTERCONNECTION WORK IS IN PROGRESS AT MANNUTHY PARAVATTANY ROAD |
Thrissur PH Dn EE |
|
25 Aug 2021 |
INTERCONNECTION WORK IS IN PROGRESS AT MANNUTHY PARAVATTANY ROAD |
Thrissur WW Sn - AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
02/08/2018 |
Scheduled date of Completion of the Project |
01 Aug 2019 |
Expected date of Completion |
24/09/2021 |
Processing Dates
AS Date |
02 Nov 2017 |
TS Date |
15 Dec 2017 |