- Home
- Project-15-RWSS to Thrikodithanam - Repl...
Project-15-RWSS to Thrikodithanam - Replacing old exising 150mm AC conveyance main line with 200mm DI K9 pipe from Mittayi company Fathimapuram to Thrikodithanam boosting pump house
| Project |
Project-15-RWSS to Thrikodithanam - Replacing old exising 150mm AC conveyance main line with 200mm DI K9 pipe from Mittayi company Fathimapuram to Thrikodithanam boosting pump house |
| Project Code |
KTMKIIFB0518768 |
| Type |
Main project |
| Category |
KIIFB |
| Description |
Replacing 3340m, 250mm AC pipe with 250mm DI K9 pipe |
| District |
Pathanamthitta |
| Execution |
P.H.Division ,Thiruvalla |
| AS Amount (Rs) |
18900000.00 |
| Total Bill Submitted (Rs) |
-- |
| Total Bill Paid (Rs) |
-- |
| Coverage |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 12 Mar 2021 |
Road cutting sanction from PWD is Pending due to non-aquirement of land by PWD for widening of roads. |
EE PHD TVLA |
|
| 12 Mar 2021 |
Road cutting sanction from PWD is Pending |
EE PHD TVLA |
|
| 17 Feb 2021 |
Road cutting sanction from PWD is Pending |
EE PHD TVLA |
|
| 16 Feb 2021 |
Road cutting sanction from PWD is pending |
EE PHD TVLA |
|
| 11 Feb 2021 |
Road cutting sanction from PWD is pending |
EE PHD TVLA |
|
No project review have been added to this project
Reported Issues
| Issue date |
Solved On |
Action Taken On |
Description |
Comments |
Issue Status |
| 31 Jan 2020 |
Pending |
Pending |
Clearance from other department |
No comments available. |
Pending |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
KIIFB_Project-15-RWSS to Thrikodithanam - Replacing old exising 150mm AC conveyance main line with 200mm DI K9 pipe from Mittayi company Fathimapuram to Thrikodithanam boosting pump house |
P.H.Division ,Thiruvalla |
|
Duration & Sanction dates
| Date of Sanction |
18/05/2018 |
| Date of start |
23/01/2020 |
| Expected date of Completion |
30/09/2021 |
Other details
| Project Officers |
View |
| Funding Agency |
KIIFB |
Processing Dates
| Administrative Sanction[AS] |
18 May 2018 |
| Technichal Sanction[TS] |
25 Nov 2019 |
| Estimate Approval |
25 Nov 2019 |
| NIT Approval |
07 Jan 2020 |
| Tender Closing |
13 Dec 2020 |
Approval Dates
| Final Approval |
07 Jan 2020 |
| Workorder Date |
07 Jan 2020 |
| Agreement Date |
23 Jan 2020 |