Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Deposit work - Nagara Sanchaya Padhadi 2020 -21 (Urban Agglomeration) WSS to ward - 3 of Porkulam Panchayath(Part 2) Erection of Pump House, Laying pumping main and allied works.

Project Deposit work - Nagara Sanchaya Padhadi 2020 -21 (Urban Agglomeration) WSS to ward - 3 of Porkulam Panchayath(Part 2) Erection of Pump House, Laying pumping main and allied works.
Project Code TCRDEPO10218977
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Nagara Sanchaya Padhadi 2020 -21 (Urban Agglomeration) WSS to ward - 3 of Porkulam Panchayath (Part 2) Erection of Pump House, Laying pumping main and allied works.
Status Completed
District Thrissur
Executing Office Guruvayur PH Sub Dn
AS Amount (Rs) 1500000
AS Number A2-2525/EST/KKM/2018
TS Amount (Rs) 1500000
TS Number 16217/2021-2022
Total Bill Submitted (Rs) 1
Total Bill Paid (Rs) 1
Population Benefitted 375
Capacity in MLD 0.05
Actual Project Completion Date Date is not specified
Coverage 2 sq. km.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Nagara Sanchaya Padhadi 2020 -21 (Urban Agglomeration) WSS to ward - 3 of Porkulam Panchayath(Part 2) Erection of Pump House, Laying pumping main and allied works. Kunnamkulam Sn
2 Nagara Sanchaya Padhadi 2020 -21 (Urban Agglomeration) WSS to ward - 3 of Porkulam Panchayath- PART 3 - Providing and placing Polyetheylene Water storage tank 5000 lit.capacity to existing base support. Kunnamkulam Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Feb 2023 Completed-bill paid. Thrissur PH Dn EE
08 Jan 2023 Completed-Ist part bill paid. Quotation work arranged under scruitiny in Division Thrissur PH Dn EE
27 Dec 2022 Work Completed. Final bill under scrutiny in Division. Thrissur PH Dn EE
01 Jun 2022 Work completed. Guruvayur PH Sub Dn - AEE
30 May 2022 Work in progress Kunnamkulam PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 24/12/2021
Scheduled date of Completion of the Project 06 Apr 2022
Expected date of Completion 23/05/2022

Processing Dates

AS Date 08 Oct 2021
TS Date 24 Dec 2021

Other details

Project Officers View