JJM-2020-21-Kallara Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy

Project JJM-2020-21-Kallara Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy
Project Code KTMJJM08204317P1
Type Package
Main Project JJM-2020-21-Kallara Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description JJM-2020-21-Kallara Panchayath - Providing 2100 Nos FHTC and Extention of pipe line 90 mm PVC Pipe - 10000 m, 110 mm PVC Pipe - 700 m , 160 mm PVC pipe - 2800 m in various wards in Kallara Panchayath .
Status On-going
District Kottayam
Executing Office Kaduthuruthy Sn
Agreement Number
Agreement Date
TS Amount (Rs) 54080000
TS Number ORDER No. TS/2020-2021/2020/14144 Dated: 27-08-2020
Technical specification Providing 2100 Nos FHTC and Extention of pipe line 90 mm PVC Pipe - 10000 m, 110 mm PVC Pipe - 700 m , 160 mm PVC pipe - 2800 m in various wards in Kallara Panchayath .
Contractor Santhosh Kumar.R (Mob: 9447213581)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 06/11/2020
Scheduled date of Completion as per agreement 15 Apr 2021
Expected date of Completion 30/08/2022

Processing Dates

TS Date 27 Aug 2020
Estimate Approval 21 Aug 2020
NIT Approval 31 Aug 2020
Tender Closing 08 Sep 2020
Technichal Pre-Qualification 31 Aug 2020
Price bid opening 11 Sep 2020

Approval Dates

Workorder Date 30 Sep 2020
NA 16 Oct 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kaduthuruthy Dn EE
Date: 19/11/2022

Work has been completed | 100% Completed

work completed.

Kaduthuruthy Dn EE
Date: 18/11/2022

Work in progress | 79% Completed

no work .