KIIFB 2021-22- PWD Deposit work - Mannarkkad Kongad Tippu Sulthan Road- Shifting utilities / pipe lines of KWA Part - I (Ch 6.300 to Ch 17.120/ NH 966 -boundary)
Project |
KIIFB 2021-22- PWD Deposit work - Mannarkkad Kongad Tippu Sulthan Road- Shifting utilities / pipe lines of KWA Part - I (Ch 6.300 to Ch 17.120/ NH 966 -boundary) |
Project Code |
PKDDEPO111611834 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
KIIFB 2021-22- PWD Deposit work - Mannarkkad Kongad Tippu Sulthan Road- Shifting utilities / pipe lines of KWA Part - I (Ch 6.300 to Ch 17.120/ NH 966 -boundary) |
Status |
On-going |
District |
Palakkad |
Executing Office |
Shornur PH Dn |
AS Amount (Rs) |
32917000
|
AS Number |
GO (Rt) No 1502/2016/PWD |
TS Amount (Rs) |
21900000 |
TS Number |
TS/2021-2022/2020/3734 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
1200 |
Capacity in MLD |
11.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Mannarkkad Kongad Tippu Sulthan Road- Shifting utilities / pipe lines of KWA Part - I (Ch 6.300 to Ch 17.120/ NH 966 -boundary) |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB 2021-22- PWD Deposit work - Mannarkkad Kongad Tippu Sulthan Road- Shifting utilities / pipe lines of KWA Part - I (Ch 6.300 to Ch 17.120/ NH 966 -boundary) |
Mannarkkad (Agali) Sn |
|
2 |
KIIFB- KRFB-PWD Deposit work - Mannarkkad Kongad Tippu Sulthan Road- Shifting utilities / pipe lines of KWA Part - II (Ch 6.300 to Ch 17.120/ NH 966 -boundary) |
Mannarkkad (Agali) Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
16 May 2024 |
Final bill submitted for approval .Pipelaying works from Karamankodavu bridge up to pallikurup junction completed on both sides also works from pallikurup towards mannarkkad (Mukkannam bridge )completed. |
Mannarkkad PH Sn AE |
|
10 May 2024 |
Final bill submitted for approval .Pipelaying works from Karamankodavu bridge up to pallikurup junction completed on both sides also works from pallikurup towards mannarkkad (Mukkannam bridge )completed. |
Mannarkkad PH Sn AE |
|
06 May 2024 |
Final bill submitted for approval .Pipelaying works from Karamankodavu bridge up to pallikurup junction completed on both sides also works from pallikurup towards mannarkkad (Mukkannam bridge )completed. |
Mannarkkad PH Sn AE |
|
02 May 2024 |
Final bill submitted for approval .Pipelaying works from Karamankodavu bridge up to pallikurup junction completed on both sides also works from pallikurup towards mannarkkad (Mukkannam bridge )completed. |
Mannarkkad PH Sn AE |
|
27 Apr 2024 |
Final bill submitted for approval .Pipelaying works from Karamankodavu bridge up to pallikurup junction completed on both sides also works from pallikurup towards mannarkkad (Mukkannam bridge )completed. |
Mannarkkad PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
15/03/2022 |
Scheduled date of Completion of the Project |
12 Oct 2022 |
Expected date of Completion |
30/12/2023 |
Processing Dates
AS Date |
01 Nov 2016 |
TS Date |
15 Mar 2022 |