Block Deposit Work-RWSS to Arakuzha-Extension of pipeline from perumballoor to Palachuvadu road in ward No.XIII of Arakuzha Panchayath
Project |
Block Deposit Work-RWSS to Arakuzha-Extension of pipeline from perumballoor to Palachuvadu road in ward No.XIII of Arakuzha Panchayath |
Project Code |
EKMDEPO022210113 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Block Deposit Work-RWSS to Arakuzha-Extension of pipeline from perumballoor to Palachuvadu road in ward No.XIII of Arakuzha Panchayath
|
Status |
Completed |
District |
Ernakulam |
Executing Office |
Muvattupuzha Sub Dn |
AS Amount (Rs) |
300000
|
AS Number |
C-240/22 |
TS Amount (Rs) |
300000 |
TS Number |
23257/2021-2022 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
500 |
Capacity in MLD |
2.00 |
Actual Project Completion Date |
30 Oct 2022 |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Block Deposit Work-RWSS to Arakuzha-Extension of pipeline from perumballoor to Palachuvadu road in ward No.XIII of Arakuzha Panchayath |
Mulanthuruthy PH Sn 1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Oct 2022 |
completed |
Koothattukulam PH Sn - AE |
|
14 Oct 2022 |
WORK IN PROGRESS |
Muvattupuzha PH Dn EE |
|
14 Oct 2022 |
WORK IN PROGRESS |
Muvattupuzha PH Dn EE |
|
10 Oct 2022 |
WORK IN PROGRESS |
Muvattupuzha PH Dn EE |
|
06 Oct 2022 |
WORK IN PROGRESS
|
Muvattupuzha PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
18/03/2022 |
Scheduled date of Completion of the Project |
30 Oct 2022 |
Expected date of Completion |
30/10/2022 |
Processing Dates
AS Date |
14 Feb 2022 |
TS Date |
18 Mar 2022 |