Project | DEPOSIT-Kochi corporation-Janakeeyasoothranam 2022-23-Laying 63mm PVC (6kg/cm2) pipe at by lane of Jawahar road,Gandhi Square in Division No-29(old) of Kochi Corporation |
---|---|
Project Code | EKMDEPO072213978P1 |
Type | Package |
Main Project | DEPOSIT-Kochi corporation-Janakeeyasoothranam 2022-23-Laying 63mm PVC (6kg/cm2) pipe at by lane of Jawahar road,Gandhi Square in Division No-29(old) of Kochi Corporation |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | DEPOSIT-Kochi corporation-Janakeeyasoothranam 2022-23-Laying 63mm PVC (6kg/cm2) pipe at by lane of Jawahar road,Gandhi Square in Division No-29(old) of Kochi Corporation |
Status | Completed |
District | Ernakulam |
Executing Office | Vytilla Section 2 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 213000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/9729/2022 |
Technical specification | agreement no.123/2022-23/AEE/WWS/VYTLA dtd 27.01.2023 |
Contractor | K N BABU (Mob: 9446489002) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 04/03/2023 |
---|---|
Scheduled date of Completion as per agreement | 27 Mar 2023 |
Expected date of Completion | 31/07/2023 |
TS Date | 05 Dec 2022 |
---|---|
Estimate Approval | 14 Jul 2022 |
NIT Approval | 19 Dec 2022 |
Tender Closing | 28 Dec 2022 |
Technichal Pre-Qualification | 28 Dec 2022 |
Price bid opening | 29 Dec 2022 |
Workorder Date | 31 Dec 2022 |
---|---|
NA | 27 Jan 2023 |
Vytilla Section AE - 2 |
Date: 19/06/2023 |
Work has been completed | 100% Completed
Bill submitted to subdivision on 05/06/2023.
Vytilla Section AE - 2 |
Date: 05/06/2023 |
Work has been completed | 100% Completed
Bill submitted to subdivision on 05/06/2023.