2021-2022 Annual Project: Vaduvacode Block panchayath deposit work in Mazhuvanoor Panchayath ward no.14 in Kattikkollil-Perumathappdam road
Project |
2021-2022 Annual Project: Vaduvacode Block panchayath deposit work in Mazhuvanoor Panchayath ward no.14 in Kattikkollil-Perumathappdam road |
Project Code |
EKMDEPO052211517 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
2021-2022 Annual Project: Vaduvacode Block panchayath deposit work in Mazhuvanoor Panchayath ward no.14 in Kattikkollil-Perumathappdam road |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Aluva PH Dn |
AS Amount (Rs) |
322000
|
AS Number |
00896 & 008695 |
TS Amount (Rs) |
322000 |
TS Number |
TS/2022-2023/2022/8081 Dated: 06-06-2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
35 |
Capacity in MLD |
0.20 |
Actual Project Completion Date |
17 Nov 2022 |
Coverage |
Ward No.14 of Mazhuvannoor Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
2021-2022 Annual Project: Vaduvacode Block panchayath deposit work in Mazhuvanoor Panchayath ward no.14 in Kattikkollil-Perumathappdam road |
Kunnathunadu PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Jul 2023 |
Work completed , Bill under preparation |
Pattimattom - Kunnathunadu AE |
|
28 Nov 2022 |
Work completed , Bill under preparation |
Pattimattom - Kunnathunadu AE |
|
26 Nov 2022 |
Work completed , Bill under preparation |
Pattimattom - Kunnathunadu AE |
|
24 Nov 2022 |
Work completed , Bill under preparation |
Pattimattom - Kunnathunadu AE |
|
23 Nov 2022 |
Bill under preparation |
Pattimattom - Kunnathunadu AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
11/07/2022 |
Scheduled date of Completion of the Project |
10 Sep 2022 |
Expected date of Completion |
10/09/2022 |
Processing Dates
AS Date |
19 May 2022 |
TS Date |
06 Jun 2022 |