Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Amrut -2017-18- THRISSSUR CORPORATION-Supply , erection, testing and commissioning of 1000 KVA 11 KV/433 KVA Transformer and connected work including construction of control panel room at WTP peechi

Project Amrut -2017-18- THRISSSUR CORPORATION-Supply , erection, testing and commissioning of 1000 KVA 11 KV/433 KVA Transformer and connected work including construction of control panel room at WTP peechi
Project Code TCRAMRUT11171101
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Erection of 1000 KVA transformer, construction of control panel ,transformer room, dedicated feeder lane from Pattikkad sub station to Peechi WTP,
Status Completed
District Thrissur
Executing Office Peechi PH Sn
AS Amount (Rs) 30000000
AS Number GO(Rt) No: 3530/2017/LSGD
TS Amount (Rs) 30000000
TS Number TS/2017-2018/2018/1806
Total Bill Submitted (Rs) 21448000
Total Bill Paid (Rs) 21448000
Population Benefitted 100000
Capacity in MLD 60.00
Actual Project Completion Date 30 Jun 2022
Coverage Thrissur corporation and adj 10 panchayat
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Amruth - Supply , errection, testing and commissioning of 1000 KVA 11 KV/433 KVA Transformer and connected work including construction of control panel room at WTP peechi Peechi PH Sn
2 AMRUT-Supply,erection, testing and commissioning of one number ,1,000 KVA 11KV/433KV Transformer and connected works including construction of control panel room at new WTP at peechi- Laying additional length of cable Peechi PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Jan 2023 Final bill to be submitted to Thrissur Corporation. Thrissur PH Dn EE
14 Oct 2022 Package 1: Bill submitted and Package 2 : Bill submitted Peechi PH Sn - AE
10 Oct 2022 Package 1: Bill submitted and Package 2 : Work Completed Peechi PH Sn - AE
03 Oct 2022 Package 1: Bill submitted and Package 2 : Work Completed Peechi PH Sn - AE
26 Sep 2022 Package 1: Bill submitted and Package 2 : Work Completed Peechi PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 05/10/2018
Scheduled date of Completion of the Project 04 Apr 2019
Expected date of Completion 14/10/2022

Processing Dates

AS Date 02 Nov 2017
TS Date 26 Mar 2018

Other details

Project Officers View