Depositwork 2019-20 RWSS to Thalavady-Relaying 90 mmm PVC line from panchayat jn to Lakshmimandiram in ward no 5
Project |
Depositwork 2019-20 RWSS to Thalavady-Relaying 90 mmm PVC line from panchayat jn to Lakshmimandiram in ward no 5 |
Project Code |
ALPDEPO02202012 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Lakshmimandiram |
Status |
Completed |
District |
Pathanamthitta |
Executing Office |
Pathanamthitta PH Circle |
AS Amount (Rs) |
339000
|
AS Number |
1(10) |
TS Amount (Rs) |
339000 |
TS Number |
TS/2020-2021/2019/19263 |
Total Bill Submitted (Rs) |
330000 |
Total Bill Paid (Rs) |
|
Population Benefitted |
200 |
Capacity in MLD |
0.10 |
Actual Project Completion Date |
15 Jun 2021 |
Coverage |
Thalavady panchayath south side |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Depositwork 2019-20 RWSS to Thalavady-Relaying 90 mmm PVC line from panchayat jn to Lakhmimandiram in ward no 5j |
Pathanamthitta PH Circle |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Sep 2021 |
bill submitted |
Thiruvalla PH Dn EE |
|
13 Aug 2021 |
bill under scrutiny |
Thiruvalla PH Dn EE |
|
01 Jun 2021 |
100% Completed |
Thiruvalla PH Dn EE |
|
08 Feb 2021 |
Completed |
Thiruvalla PH Dn EE |
|
03 Feb 2021 |
ongoing |
Thiruvalla PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
07/10/2020 |
Scheduled date of Completion of the Project |
16 Jun 2021 |
Expected date of Completion |
15/06/2021 |
Processing Dates
AS Date |
13 Feb 2020 |
TS Date |
09 Jun 2020 |