Deposit work of Kundara Panchayath- BAWSS Kundara and adjoining pts. - Pipe line extension in various wards of Kundara Panchayath
Project |
Deposit work of Kundara Panchayath- BAWSS Kundara and adjoining pts. - Pipe line extension in various wards of Kundara Panchayath |
Project Code |
KLMDEPO042211060 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work of Kundara Panchayath- BAWSS Kundara and adjoining pts. - Pipe line extension in various wards of Kundara Panchayath |
Status |
Completed |
District |
Kollam |
Executing Office |
Kundara PH Sn |
AS Amount (Rs) |
702800
|
AS Number |
A101/22 |
TS Amount (Rs) |
702800 |
TS Number |
TS/2022-2023/2022/11982 |
Total Bill Submitted (Rs) |
534046 |
Total Bill Paid (Rs) |
534046 |
Population Benefitted |
|
Capacity in MLD |
16.00 |
Actual Project Completion Date |
02 Jun 2022 |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work of Kundara Panchayath- BAWSS Kundara and adjoining pts. - Pipe line extension in various wards of Kundara Panchayath |
Kundara PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Jul 2022 |
Work completed |
Kundara PH Sn - AE |
|
01 Jul 2022 |
PIPE LAYING WORK IN PROGRESS |
Kottarakkara PH Dn EE |
|
28 Jun 2022 |
PIPE LAYING WORK IN PROGRESS |
Kottarakkara PH Dn EE |
|
25 Jun 2022 |
pipe laying work in progress |
Kottarakkara PH Dn EE |
|
20 Jun 2022 |
GI pipe laying work in progress |
Kottarakkara PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
16 Jun 2022 |
Expected date of Completion |
16/06/2022 |
Processing Dates
AS Date |
02 Apr 2022 |
TS Date |
08 Apr 2022 |