State plan- Replacement of damaged pipes- RWSS to Bhoomivathukkal- Replacing 125& 100mm AC distribution main using 140& 110mm PVC class 5 pipe for a length of 4550mtr

Project State plan- Replacement of damaged pipes- RWSS to Bhoomivathukkal- Replacing 125& 100mm AC distribution main using 140& 110mm PVC class 5 pipe for a length of 4550mtr
Project Code CLTGOK02161347
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State plan- Replacement of damaged pipes- RWSS to Bhoomivathukkal- Replacing 125& 100mm AC distribution main using 140& 110mm PVC class 5 pipe for a length of 4550mtr
Status Dropped
District Kozhikkode
Executing Office Vadakara WSP Sub Dn
AS Amount (Rs) 5400000
AS Number GO ( Rt ) No: 149/2016 WRD dt 17.02.2016
TS Amount (Rs) 5400000
TS Number SE/PHC/KKD/04/2015-17
Total Bill Submitted (Rs) 3204017
Total Bill Paid (Rs) 3204017
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage Bhoomivathukkal

Packages

No. Project Name Location View
1 State plan- Replacement of damaged pipes- RWSS to Bhoomivathukkal- Replacing 125& 100mm AC distribution main using 140& 110mm PVC class 5 pipe for a length of 4550mtr Vadakara WSP Sub Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Aug 2022 Work proposed to Drop Purameri PH Sn - AE
26 Aug 2022 Work proposed to Drop Purameri PH Sn - AE
22 Aug 2022 Work proposed to Drop Purameri PH Sn - AE
16 Aug 2022 Work proposed to Drop Purameri PH Sn - AE
11 Aug 2022 Work proposed to Drop Purameri PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project 19 May 2017
Expected date of Completion 31/03/2021

Processing Dates

AS Date 17 Feb 2016
TS Date 30 Sep 2016

Other details

Project Officers View