| Project | JJM -Kannur District Dharmadam Panchayaths WSS to Thalassery Mahe & adjoining Panchayaths -Phase II |
|---|---|
| Project Code | KNRJJM08202932P1 |
| Type | Package |
| Main Project | JJM-Kannur District- Dharmadam Panchayath-WSS to Thalassery, Mahe and adjoining Panchayaths - Phase II |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Laying Distribution system and providing FHTCs |
| Status | On-going |
| District | Kannur |
| Executing Office | Thalassery PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 98100000 |
| TS Number | TS/2020-2021/2020/19114 |
| Technical specification | |
| Contractor | E.V.RAJU (Mob: 9447764227) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 26/10/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 08 Apr 2021 |
| Expected date of Completion | 28/02/2022 |
| TS Date | 26 Aug 2021 |
|---|---|
| Estimate Approval | 26 Aug 2020 |
| Workorder Date | 09 Oct 2020 |
|---|---|
| NA | 09 Nov 2020 |
| Thalassery PH Sn AE |
| Date: 13/07/2022 |
Work has been completed | 100% Completed
Work completed & Final bill submited.
| Thalassery PH Sn AE |
| Date: 06/05/2022 |
Work in progress | 88% Completed
3720 FHTC GIVEN &28.3 KM PIPE LINE LAID .