Project | JJM -Kannur District Dharmadam Panchayaths WSS to Thalassery Mahe & adjoining Panchayaths -Phase II |
---|---|
Project Code | KNRJJM08202932P1 |
Type | Package |
Main Project | JJM-Kannur District- Dharmadam Panchayath-WSS to Thalassery, Mahe and adjoining Panchayaths - Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Laying Distribution system and providing FHTCs |
Status | On-going |
District | Kannur |
Executing Office | Thalassery PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 98100000 |
TS Number | TS/2020-2021/2020/19114 |
Technical specification | |
Contractor | E.V.RAJU (Mob: 9447764227) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 26/10/2020 |
---|---|
Scheduled date of Completion as per agreement | 08 Apr 2021 |
Expected date of Completion | 28/02/2022 |
TS Date | 26 Aug 2021 |
---|---|
Estimate Approval | 26 Aug 2020 |
Workorder Date | 09 Oct 2020 |
---|---|
NA | 09 Nov 2020 |
Thalassery PH Sn AE |
Date: 13/07/2022 |
Work has been completed | 100% Completed
Work completed & Final bill submited.
Thalassery PH Sn AE |
Date: 06/05/2022 |
Work in progress | 88% Completed
3720 FHTC GIVEN &28.3 KM PIPE LINE LAID .