Deposit work 2017-18 Madappally Block panchayath (Thrikodithanam division) RWSS to Thrikodithanam- Pipe line extension to Manimury- Mechery Colony in thrikkodithanam Panchayath

Project Deposit work 2017-18 Madappally Block panchayath (Thrikodithanam division) RWSS to Thrikodithanam- Pipe line extension to Manimury- Mechery Colony in thrikkodithanam Panchayath
Project Code KTMDEPO03182347
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work 2017-18 Madappally Block panchayath (Thrikodithanam division) RWSS to Thrikodithanam- Pipe line extension to Manimury- Mechery Colony in thrikkodithanam Panchayath
Status Completed
District Kottayam
Executing Office Changanassery Sn
AS Amount (Rs) 920000
AS Number Deposit Thrikkodithanam
TS Amount (Rs) 500000
TS Number TS/2020-2021/2019/4918
Total Bill Submitted (Rs) 162013
Total Bill Paid (Rs) 162013
Population Benefitted 2500
Capacity in MLD 0.08
Actual Project Completion Date 04 Dec 2020
Coverage 100% Completed
Work Plan Download

Packages

No. Project Name Location View
1 Deposit work 2017-18 Madappally Block panchayath (Thrikodithanam division) RWSS to Thrikodithanam- Pipe line extension to Manimury- Mechery Colony in thrikkodithanam Panchayath Changanassery Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Jun 2021 100% Completed Thiruvalla PH Dn EE
02 Feb 2021 WORKCOMPLETED-BILL UNDER SCRUTINING Thiruvalla PH Dn EE
24 Nov 2020 Completed Thiruvalla PH Dn EE
19 Nov 2020 90% COMPLETED Thiruvalla PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 17/06/2019
Scheduled date of Completion of the Project 04 Dec 2020
Expected date of Completion 04/12/2020

Processing Dates

AS Date 27 Mar 2018
TS Date 20 Apr 2018

Other details

Project Officers View