Deposit work - Pavithreswaram Grama Panchayath for the financial year 2021-22 - ARWSS to Kulakkada and Pavithreswaram-Line extension at various wards of Pavithreswaram Grama Panchayath
Project |
Deposit work - Pavithreswaram Grama Panchayath for the financial year 2021-22 - ARWSS to Kulakkada and Pavithreswaram-Line extension at various wards of Pavithreswaram Grama Panchayath |
Project Code |
KLMDEPO042211067 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work - Pavithreswaram Grama Panchayath for the financial year 2021-22 - ARWSS to Kulakkada and Pavithreswaram-Line extension at various wards of Pavithreswaram Grama Panchayath |
Status |
Completed |
District |
Kollam |
Executing Office |
Kottarakkara PH Sn |
AS Amount (Rs) |
2145430
|
AS Number |
A4.111/2022 |
TS Amount (Rs) |
2145400 |
TS Number |
1058/2022-2023 |
Total Bill Submitted (Rs) |
1381063 |
Total Bill Paid (Rs) |
1381063 |
Population Benefitted |
500 |
Capacity in MLD |
0.25 |
Actual Project Completion Date |
26 Sep 2022 |
Coverage |
various wards of Pavithreswaram Grama Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work - Pavithreswaram Grama Panchayath for the financial year 2021-22 - ARWSS to Kulakkada and Pavithreswaram-Line extension at various wards of Pavithreswaram Grama Panchayath |
Kottarakkara PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
23 Jan 2024 |
Completed. Bill submitted |
Kottarakkara PH Sn - AE |
|
01 Dec 2023 |
Completed.Bill submitted |
Kottarakkara PH Sn - AE |
|
29 Dec 2022 |
Work Completed, Bill submitted. |
Kottarakkara PH Sn - AE |
|
30 Sep 2022 |
bill under processining |
Kottarakkara PH Sn - AE |
|
26 Sep 2022 |
Work completed |
Kottarakkara PH Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
18/05/2022 |
Scheduled date of Completion of the Project |
17 Aug 2022 |
Expected date of Completion |
24/09/2022 |
Processing Dates
AS Date |
07 Apr 2022 |
TS Date |
18 Apr 2022 |