Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

State Plan 2023- 24 Mace of WSS to Puthencuz & adjoing panchayath - world bank pump house - Supply erection, commissioning and trial run of split case centrifugal pump set and VT pump set at Choondy CWPH and Ramamangalam RWPH and allied works

Project State Plan 2023- 24 Mace of WSS to Puthencuz & adjoing panchayath - world bank pump house - Supply erection, commissioning and trial run of split case centrifugal pump set and VT pump set at Choondy CWPH and Ramamangalam RWPH and allied works
Project Code EKMGOK052314396
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State Plan 2023- 24 Mace of WSS to Puthencuz & adjoing panchayath - world bank pump house - Supply erection, commissioning and trial run of split case centrifugal pump set and VT pump set at Choondy CWPH and Ramamangalam RWPH and allied works
Status On-going
District Ernakulam
Executing Office Kochi WS Dn
AS Amount (Rs) 10500000
AS Number KWA-JB/4200/2023-AE 4
TS Amount (Rs) 1556000
TS Number WRD/KWA-CE(CR)/EST_TS/9849/2022_5_1_1
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage Supply erection, commissioning and trial run of split case centrifugal pump set and VT pump set at Choondy

Packages

No. Project Name Location View
1 State Plan 2023- 24 Mace of WSS to Puthencuz & adjoing panchayath - world bank pump house - Supply erection, commissioning and trial run of split case centrifugal pump set and VT pump set at Choondy CWPH and Ramamangalam RWPH and allied works Puthencruz WS Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 May 2024 Revised AS obtained submitted to circle for TS Approval . Kochi WS Dn EE
27 Mar 2024 Revised AS obtained Awaiting TS Approval Kochi WS Dn EE
19 Mar 2024 Revised AS obtained Awaiting TS Approval Kochi WS Dn EE
14 Feb 2024 Revised AS obtained, Estimate submitted to circle for TS Approval Kochi WS Dn EE
08 Feb 2024 Revised AS obtained, Estimate submitted to circle for TS Approval Kochi WS Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 31/08/2024

Processing Dates

AS Date 06 Jan 2024
TS Date 16 Sep 2023

Other details

Project Officers View