Augumentation of WSS to N Paravur Municipality and adjoining Pts. - Supply, Erection, Testing &commissioning of 1 Nos. 90 HP best Quality reputed make centrifugal pump set having a discharge of 78.5lps against a total head of 55 m at N Paravur Pump House . Water supply for Kottuvally and Ezhikkara pt.
Project |
Augumentation of WSS to N Paravur Municipality and adjoining Pts. - Supply, Erection, Testing &commissioning of 1 Nos. 90 HP best Quality reputed make centrifugal pump set having a discharge of 78.5lps against a total head of 55 m at N Paravur Pump House . Water supply for Kottuvally and Ezhikkara pt. |
Project Code |
EKMGOK08184056 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Augumentation of WSS to N Paravur Municipality and adjoining Pts. - Supply, Erection, Testing &commissioning of 1 Nos. 90 HP best Quality reputed make centrifugal pump set having a discharge of 78.5lps against a total head of 55 m at N Paravur Pump House . Water supply for Kottuvally and Ezhikkara pt. |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Kochi WS Dn |
AS Amount (Rs) |
1500000
|
AS Number |
G.O. (Rt)No.615/2018/WRD |
TS Amount (Rs) |
|
TS Number |
|
Total Bill Submitted (Rs) |
1216960 |
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
30 Jun 2020 |
Coverage |
Kottuvally and Ezhikkara panchayath area |
Packages
No. |
Project Name |
Location |
View |
1 |
Augumentation of WSS to N Paravur Municipality and adjoining Pts. - Supply, Erection, Testing &commissioning of 1 Nos. 90 HP best Quality reputed make centrifugal pump set having a discharge of 78.5lps against a total head of 55 m at N Paravur Pump House . Water supply for Kottuvally and Ezhikkara pt. |
WS Division Kochi |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Nov 2020 |
completed and bill submitted |
Kochi WS Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
28/02/2020 |
Scheduled date of Completion of the Project |
Date is not specified |
Expected date of Completion |
30/06/2020 |
Processing Dates
AS Date |
20 Aug 2018 |
TS Date |
30 Nov 2018 |