DEPOSIT- Kochi Corporation - Laying 110mm PVC pipe line in the place of old damaged 100mm AC pipe line in Mahilasamagam road, Vennala division no 33(old) ( new 42) of Kochi Corporation-Pipeline Work
Project |
DEPOSIT- Kochi Corporation - Laying 110mm PVC pipe line in the place of old damaged 100mm AC pipe line in Mahilasamagam road, Vennala division no 33(old) ( new 42) of Kochi Corporation-Pipeline Work |
Project Code |
EKMDEPO072215227 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
DEPOSIT- Kochi Corporation - Laying 110mm PVC pipe line in the place of old damaged 100mm AC pipe line in Mahilasamagam road, Vennala division no 33(old) ( new 42) of Kochi Corporation-Pipeline Work |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Vytilla Section 1 |
AS Amount (Rs) |
1893000
|
AS Number |
A7-191/2021 |
TS Amount (Rs) |
1910000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/9589/2022_26_1_1 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
260 |
Capacity in MLD |
1.00 |
Actual Project Completion Date |
15 Jan 2024 |
Coverage |
100% completed |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT- Kochi Corporation - Laying 110mm PVC pipe line in the place of old damaged 100mm AC pipe line in Mahilasamagam road, Vennala division no 33(old) ( new 42) of Kochi Corporation-Pipeline Work |
Vytilla Section 1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
22 Mar 2024 |
Bill submitted |
Vytilla Section AE - 1 |
|
18 Mar 2024 |
Bill under preparation |
Vytilla Section AE - 1 |
|
14 Mar 2024 |
Bill under preparation |
Vytilla Section AE - 1 |
|
28 Feb 2024 |
Bill under preparation |
Vytilla Section AE - 1 |
|
19 Feb 2024 |
Bill under preparation |
Vytilla Section AE - 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
13/12/2023 |
Scheduled date of Completion of the Project |
26 Mar 2023 |
Expected date of Completion |
31/01/2024 |
Processing Dates
AS Date |
14 Jul 2022 |
TS Date |
23 Jan 2023 |