- Home
- DEPOSIT-Deposit Work:thrissur Corporatio...
DEPOSIT-Deposit Work:thrissur Corporation-Pipe line Extension at Nedupuzha Division 44-Thrissur Corporation-Pipeline Work-1-Additional works
Project |
DEPOSIT-Deposit Work:thrissur Corporation-Pipe line Extension at Nedupuzha Division 44-Thrissur Corporation-Pipeline Work-1-Additional works |
Project Code |
TCRDEPO102315755 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
DEPOSIT-Deposit Work:thrissur Corporation-Pipe line Extension at Nedupuzha Division 44-Thrissur Corporation-Pipeline Work-1-Additional works |
Status |
Completed |
District |
Thrissur |
Executing Office |
Thrissur WW Sub Dn |
AS Amount (Rs) |
5000000
|
AS Number |
48371 dated 16-03-2023 |
TS Amount (Rs) |
1500000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/8838/2022_26_7_6 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT-Deposit Work:thrissur Corporation-Pipe line Extension at Nedupuzha Division 44-Thrissur Corporation-Pipeline Work-1-Additional works |
Thrissur WW Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
22 Apr 2024 |
Work completed. Bill under preparation. |
Thrissur PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
25/01/2024 |
Scheduled date of Completion of the Project |
24 Jul 2024 |
Expected date of Completion |
24/07/2024 |
Processing Dates
AS Date |
10 Oct 2023 |
TS Date |
11 Jan 2024 |