Deposit Work of National Skill Training Institute for Women Thiruvananthapuram: Alteration of the existing Water connection of National Skill Training Institute (Women ) by providing 63mm PVC pipe (10kg/cm2 ) for a length of 40m from 250mm CI line( CRPF ) at Kazhakuttom, Thiruvananthapuram
Project |
Deposit Work of National Skill Training Institute for Women Thiruvananthapuram: Alteration of the existing Water connection of National Skill Training Institute (Women ) by providing 63mm PVC pipe (10kg/cm2 ) for a length of 40m from 250mm CI line( CRPF ) at Kazhakuttom, Thiruvananthapuram |
Project Code |
TVMDEPO072212200 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit Work of National Skill Training Institute for Women Thiruvananthapuram: Alteration of the existing Water connection of National Skill Training Institute (Women ) by providing 63mm PVC pipe (10kg/cm2 ) for a length of 40m from 250mm CI line( CRPF ) at Kazhakuttom, Thiruvananthapuram |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Kazhakootam WW Sn |
AS Amount (Rs) |
411000
|
AS Number |
NSTIT/D11014/Minor works/2022/civil/275 |
TS Amount (Rs) |
411000 |
TS Number |
9883/2022-2023 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
200 |
Capacity in MLD |
0.05 |
Actual Project Completion Date |
24 Nov 2022 |
Coverage |
Work proposed as alteration for RVTI by laying 63 mm PVC pipe and abandoning old GI Line |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit Work of National Skill Training Institute for Women Thiruvananthapuram: Alteration of the existing Water connection of National Skill Training Institute (Women ) by providing 63mm PVC pipe (10kg/cm2 ) for a length of 40m from 250mm CI line( CRPF ) at Kazhakuttom, Thiruvananthapuram |
Kazhakootam WW Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
15 May 2024 |
NHAI permission pending |
Kazhakootam WW Sn AE |
|
08 May 2024 |
NHAI permission pending |
Kazhakootam WW Sn AE |
|
06 May 2024 |
NHAI permission pending |
Kazhakootam WW Sn AE |
|
03 May 2024 |
NHAI permission pending |
Kazhakootam WW Sn AE |
|
23 Apr 2024 |
NHAI permission pending |
Kazhakootam WW Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
24/08/2022 |
Scheduled date of Completion of the Project |
24 Nov 2022 |
Expected date of Completion |
24/11/2022 |
Processing Dates
AS Date |
07 Jul 2022 |
TS Date |
13 Jul 2022 |