STATE PLAN 2016-17 RWSS Pudussery shiftins distribution main passing through RLY coach factory 160 mm pvc

Project STATE PLAN 2016-17 RWSS Pudussery shiftins distribution main passing through RLY coach factory 160 mm pvc
Project Code PKDGOK02171014
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State Plan - 2016 - 17 - Optimisation - Rwss to Pudussery - Shifting distribution main passing through Rail Coach Factory, Palakkad - 160mm PVC pipe
Status On-going
District Palakkad
Executing Office Palakkad Revenue Sn
AS Amount (Rs) 10000000
AS Number GO(Rt)No 119/2017/WRD
TS Amount (Rs) 7900000
TS Number TS/2018-19/2018/2055
Total Bill Submitted (Rs) 3484698
Total Bill Paid (Rs) 3484698
Population Benefitted 20000
Capacity in MLD 4.50
Actual Project Completion Date 04 Sep 2022
Coverage State Plan - 2016 - 17 - Optimisation - Rwss to Pudussery - Shifting distribution main passing through Rail Coach Factory, Palakkad - 160mm PVC pipe 90% completed
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 STATE PLAN 2016-17 RWSS Pudussery shiftins distribution main passing through RLY coach factory 160 mm pvc-part -1/2-rail way crossing ,two chambers ,valve fitting etc Malampuzha Sn
2 STATE PLAN 2016-17 RWSS Pudussery shiftins distribution main passing through RLY coach factory 160 mm pvc-part 2/2 -pipe line work Malampuzha Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Feb 2024 work not started Malampuzha Sn AE
02 Feb 2024 work not started Malampuzha Sn AE
27 Jan 2024 WORK NOT STARTED Malampuzha Sn AE
12 Jan 2024 work not started Malampuzha Sn AE
04 Jan 2024 WORK NOT STARTED Malampuzha Sn AE

Project Review

See All Review messages
Review Date Review Message Review Attended By
10 Mar 2021 State Plan - 2016 - 17 - Optimisation - Rwss to Pudussery - Shifting distribution main passing through Rail Coach Factory, Palakkad - 160mm PVC pipe 90% completed

Duration & Sanction dates

Date of start of Project 30/10/2018
Scheduled date of Completion of the Project 16 Mar 2019
Expected date of Completion 04/09/2022

Processing Dates

AS Date 14 Feb 2017
TS Date 31 May 2018

Other details

Project Officers View