- Home
- Improving water supply to Sree Narayana...
Improving water supply to Sree Narayana Road by Laying 90 mm PVC in Div 49 & 50 (old) of Kochi Corporation
Project |
Improving water supply to Sree Narayana Road by Laying 90 mm PVC in Div 49 & 50 (old) of Kochi Corporation |
Project Code |
EKMDEPO |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Improving water supply to Sree Narayana Road by Laying 90 mm PVC in Div 49 & 50 (old) of Kochi Corporation |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Kaloor WW Sn 2 |
AS Amount (Rs) |
1070000
|
AS Number |
18254/2023_26_1_1 |
TS Amount (Rs) |
1070000 |
TS Number |
11495/2023-2024 |
Total Bill Submitted (Rs) |
1 |
Total Bill Paid (Rs) |
1 |
Population Benefitted |
2000 |
Capacity in MLD |
5.00 |
Actual Project Completion Date |
12 Feb 2024 |
Coverage |
Sree Narayana Road |
Packages
No. |
Project Name |
Location |
View |
1 |
Improving water supply to Sree Narayana Road by Laying 90 mm PVC in Div 49 & 50 (old) of Kochi Corporation |
Kaloor WW Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
06 May 2024 |
work completed, Bill under preparation |
Kaloor AE 2 |
|
29 Apr 2024 |
work completed, Bill under preparation |
Kaloor AE 2 |
|
19 Apr 2024 |
work completed |
Kaloor AE 2 |
|
03 Apr 2024 |
work completed |
Kaloor AE 2 |
|
23 Mar 2024 |
work completed |
Kaloor AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
06/10/2023 |
Scheduled date of Completion of the Project |
Date is not specified |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
09 Jun 2022 |
TS Date |
08 Aug 2023 |