Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Augmentation of water supply scheme to Thripunithura municipality &adjoining panchayath -Supply, Errection, testing and commissioning of 2 Nos of VT pumpsets with a discharge of 266 lps against a total head of 67 m and having a minimum efficiency of 70% at Raw water pump house, ramamangalam and supply, errection, testting and commissioning of additional VCB inside transformer substation building at Ramamangalam and allied works

Project Augmentation of water supply scheme to Thripunithura municipality &adjoining panchayath -Supply, Errection, testing and commissioning of 2 Nos of VT pumpsets with a discharge of 266 lps against a total head of 67 m and having a minimum efficiency of 70% at Raw water pump house, ramamangalam and supply, errection, testting and commissioning of additional VCB inside transformer substation building at Ramamangalam and allied works
Project Code EKMGOK10145100P2
Type Package
Main Project Augmentation of water supply scheme to Thripunithura municipality &adjoining panchayath
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Augmentation of water supply scheme to Thripunithura municipality &adjoining panchayath -Supply, Errection, testing and commissioning of 2 Nos of VT pump sets with a discharge of 266 lps against a total head of 67 m and having a minimum efficiency of 70% at Raw water pump house, ramamangalam and supply, erection, testing and commissioning of additional VCB inside transformer substation building at Ramamangalam and allied works
Status Completed
District Ernakulam
Executing Office Kochi WS Dn
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification Supply, Errection, testing and commissioning of 2 Nos of VT pump sets with a discharge of 266 lps against a total head of 67 m and having a minimum efficiency of 70% at Raw water pump house, ramamangalam and supply, erection, testing and commissioning of additional VCB inside transformer substation building at Ramamangalam and allied works

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 23/06/2017
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 15/11/2017

Processing Dates

AS Date 15 Oct 2014
TS Date 22 Nov 2014
Estimate Approval 22 Nov 2014
Tender Closing 02 May 2017
Technichal Pre-Qualification 12 May 2017
Price bid opening 05 May 2017

Approval Dates

CE Approval 31 May 2017
Workorder Date 23 Jun 2017
NA 04 Jul 2017

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kochi WS Dn EE
Date: 23/11/2020

Work has been completed | 100% Completed

Work completed and bill submitted.