- Home
- State Plan 2022-2023 -JICA Assisted WSS...
State Plan 2022-2023 -JICA Assisted WSS to Pattuvam and Adjoining villages-Mace of 90 MLD WTP at Peruvalathuparamba - Providing barbed wire fencing at WTP Peruvalathuparamba .-General Civil Work
Project |
State Plan 2022-2023 -JICA Assisted WSS to Pattuvam and Adjoining villages-Mace of 90 MLD WTP at Peruvalathuparamba - Providing barbed wire fencing at WTP Peruvalathuparamba .-General Civil Work |
Project Code |
KNRGOK062213228 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Mace of 90 MLD WTP at Peruvalathuparamba - Providing barbed wire fencing at WTP Peruvalathuparamba . |
Status |
On-going |
District |
Kannur |
Executing Office |
Irikkur HW Sn |
AS Amount (Rs) |
1332000
|
AS Number |
KWA/JB/PIU1/AE4/1/2022( |
TS Amount (Rs) |
1180000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/3609/2022_5_7_6 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
300000 |
Capacity in MLD |
93.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Kannur corporation (part1) Andoor, Taliparamba |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JICA Assisted WSS to Pattuvam and Adjoining villages-JICA Assisted WSS to Pattuvam and Adjoining villages-Mace of 90 MLD WTP at Peruvalathuparamba - Providing barbed wire fencing at WTP Peruvalathuparamba .-General Civil Work |
Irikkur HW Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
17 May 2024 |
The original estimate was prepared in PRICE 1 and tendered several times . Due to no offers,the TS was cancelled and estimate recast in PRICE 3 .NO OFFERS RECEIVED IN TENDER.Hence retendered |
Thaliparamba WS Dn EE |
|
16 May 2024 |
The original estimate was prepared in PRICE 1 and tendered several times . Due to no offers,the TS was cancelled and estimate recast in PRICE 3 .NO OFFERS RECEIVED IN TENDER.Hence retendered |
Thaliparamba WS Dn EE |
|
15 May 2024 |
The original estimate was prepared in PRICE 1 and tendered several times . Due to no offers,the TS was cancelled and estimate recast in PRICE 3 .NO OFFERS RECEIVED IN TENDER.Hence retendered |
Thaliparamba WS Dn EE |
|
14 May 2024 |
The original estimate was prepared in PRICE 1 and tendered several times . Due to no offers,the TS was cancelled and estimate recast in PRICE 3 .NO OFFERS RECEIVED IN TENDER.Hence retendered |
Thaliparamba WS Dn EE |
|
13 May 2024 |
The original estimate was prepared in PRICE 1 and tendered several times . Due to no offers,the TS was cancelled and estimate recast in PRICE 3 .NO OFFERS RECEIVED IN TENDER.Hence retendered |
Thaliparamba WS Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
Date is not specified |
Expected date of Completion |
31/12/2023 |
Processing Dates
AS Date |
14 Jun 2022 |
TS Date |
13 Dec 2022 |