Deposit work- 2020-21- Angamaly Block Panchayath -(Project No.145 / 21) - Providing 27 nos water supply connections at Tharanilam Colony in Ward 14 of Kanjoor Panchayath.
Project |
Deposit work- 2020-21- Angamaly Block Panchayath -(Project No.145 / 21) - Providing 27 nos water supply connections at Tharanilam Colony in Ward 14 of Kanjoor Panchayath. |
Project Code |
EKMDEPO11208361 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work- 2020-21- Angamaly Block Panchayath -(Project No.145 / 21) - Providing 27 nos water supply connections at Tharanilam Colony in Ward 14 of Kanjoor Panchayath. |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Chowara HW Sn |
AS Amount (Rs) |
470000
|
AS Number |
Receipt No:008537 PH Div aluva dated:02.08.2021 |
TS Amount (Rs) |
470000 |
TS Number |
TS/2021-2022/2020/20405 Dated: 20-12-2021 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
500 |
Capacity in MLD |
0.10 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Receipt No:008537 PH Div aluva dated:02.08.2021 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work- 2020-21- Angamaly Block Panchayath -(Project No.145 / 21) - Providing 27 nos water supply connections at Tharanilam Colony in Ward 14 of Kanjoor Panchayath. |
Chowara HW Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
23 May 2022 |
work completed |
Chowara AE |
|
20 May 2022 |
Work going on 87% completed |
Chowara AE |
|
18 May 2022 |
Work going on 86% completed |
Chowara AE |
|
16 May 2022 |
Work going on 85% completed |
Chowara AE |
|
13 May 2022 |
Work going on 84% completed |
Chowara AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
18/01/2022 |
Scheduled date of Completion of the Project |
17 Apr 2022 |
Expected date of Completion |
17/04/2022 |
Processing Dates
AS Date |
02 Aug 2021 |
TS Date |
20 Dec 2021 |