Alappuzha District Panchayat Deposit work -SCP - 2019 -20 -RWSS to Chennithala - Pipe line extension from various wards( ward-1, 14 &17) at Chennithala Grama Panchayat
Project |
Alappuzha District Panchayat Deposit work -SCP - 2019 -20 -RWSS to Chennithala - Pipe line extension from various wards( ward-1, 14 &17) at Chennithala Grama Panchayat |
Project Code |
ALPDEPO04204237 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Alappuzha District Panchayat Deposit work -SCP - 2019 -20 -RWSS to Chennithala - Pipe line extension from various wards( ward-1, 14 &17) at Chennithala Grama Panchayat |
Status |
Completed |
District |
Alappuzha |
Executing Office |
Alappuzha PH Dn |
AS Amount (Rs) |
720000
|
AS Number |
100241/2020 |
TS Amount (Rs) |
720000 |
TS Number |
TS 6745/2020-21 |
Total Bill Submitted (Rs) |
435438 |
Total Bill Paid (Rs) |
435438 |
Population Benefitted |
780 |
Capacity in MLD |
0.50 |
Actual Project Completion Date |
23 Nov 2020 |
Coverage |
Covering the SC colonies in ward No 1,4 &17 of Chennithala panchayath. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Alappuzha District Panchayat Deposit work -SCP - 2019 -20 -RWSS to Chennithala - Pipe line extension from various wards( ward-1, 14 &17) at Chennithala Grama Panchayat |
Chengannur WS Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Aug 2021 |
Work Completed On 23.11.2020 |
Alappuzha PH Dn EE |
|
20 Jul 2021 |
Work Completed On 23.11.2020 |
Alappuzha PH Dn EE |
|
19 Jul 2021 |
Bill Submitted |
Alappuzha PH Dn EE |
|
05 Jul 2021 |
Bill Submitted |
Alappuzha PH Dn EE |
|
01 Jun 2021 |
Bill Submitted |
Alappuzha PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
06/10/2020 |
Scheduled date of Completion of the Project |
26 Nov 2020 |
Expected date of Completion |
15/02/2021 |
Processing Dates
AS Date |
02 Apr 2020 |
TS Date |
09 Sep 2020 |