Deposit work (2021-22)-WSS to Mananthavady,Edavaka and Nalloornadu Villages -Providing drinking water supply to Pathivayal colony in Mananthavady Municipality

Project Deposit work (2021-22)-WSS to Mananthavady,Edavaka and Nalloornadu Villages -Providing drinking water supply to Pathivayal colony in Mananthavady Municipality
Project Code WYDDEPO12219170P1
Type Package
Main Project Deposit work (2021-22)-WSS to Mananthavady,Edavaka and Nalloornadu Villages -Providing drinking water supply to Pathivayal colony in Mananthavady Municipality
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work (2021-22)-WSS to Mananthavady,Edavaka and Nalloornadu Villages -Providing drinking water supply to Pathivayal colony in Mananthavady Municipality
Status On-going
District Wayanad
Executing Office Mananthavady PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 43000
TS Number TS/2021-2022/2021/18969
Technical specification Deposit work (2021-22)-WSS to Mananthavady,Edavaka and Nalloornadu Villages -Providing drinking water supply to Pathivayal colony in Mananthavady Municipality
Contractor Aneesh Abraham (Mob: 9562250601)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 07/12/2022
Scheduled date of Completion as per agreement 30 Jun 2022
Expected date of Completion 31/03/2022

Processing Dates

TS Date 08 Feb 2022
Technichal Pre-Qualification 28 Sep 2021

Approval Dates

Workorder Date 28 Sep 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Sulthan Bathery PH Dn EE
Date: 31/03/2022

Work has been completed | 100% Completed

Connection given. Work completed..

Sulthan Bathery PH Dn EE
Date: 26/03/2022

Work in progress | 70% Completed

Work is progressing. 70% completed.