Project | Deposit work (2021-22)-WSS to Mananthavady,Edavaka and Nalloornadu Villages -Providing drinking water supply to Pathivayal colony in Mananthavady Municipality |
---|---|
Project Code | WYDDEPO12219170P1 |
Type | Package |
Main Project | Deposit work (2021-22)-WSS to Mananthavady,Edavaka and Nalloornadu Villages -Providing drinking water supply to Pathivayal colony in Mananthavady Municipality |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | Deposit work (2021-22)-WSS to Mananthavady,Edavaka and Nalloornadu Villages -Providing drinking water supply to Pathivayal colony in Mananthavady Municipality |
Status | On-going |
District | Wayanad |
Executing Office | Mananthavady PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 43000 |
TS Number | TS/2021-2022/2021/18969 |
Technical specification | Deposit work (2021-22)-WSS to Mananthavady,Edavaka and Nalloornadu Villages -Providing drinking water supply to Pathivayal colony in Mananthavady Municipality |
Contractor | Aneesh Abraham (Mob: 9562250601) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 07/12/2022 |
---|---|
Scheduled date of Completion as per agreement | 30 Jun 2022 |
Expected date of Completion | 31/03/2022 |
TS Date | 08 Feb 2022 |
---|---|
Technichal Pre-Qualification | 28 Sep 2021 |
Workorder Date | 28 Sep 2021 |
---|
Sulthan Bathery PH Dn EE |
Date: 31/03/2022 |
Work has been completed | 100% Completed
Connection given. Work completed..
Sulthan Bathery PH Dn EE |
Date: 26/03/2022 |
Work in progress | 70% Completed
Work is progressing. 70% completed.