KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths Package I
| Project |
KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths Package I |
| Project Code |
ALPKIIFB0619496P2 |
| Type |
Package |
| Main Project |
KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths
|
| Funding Agency |
KIIFB |
| Category |
KIIFB WATER SUPPLY SCHEME |
| Type of scheme |
Water Supply |
| Scheme |
KIIFB |
| Description |
Construction of 16 LL OHSR and 5 LL Sump at Chathanad in Alappuzha Municiplaity Construction of 16 LL OHSR and 3 LL Sump at Vadikadu in Alappuzha Municiplaity Construction of 12 LL OHSR and 3 LL Sump cum pump house at Kattoor in Mararikulam South Pt Construction of Operator Quarters Laying clear Water Pumping main Kulamakki to OHSR (R20) at FHC Kattoor – 280mm HDPE - 2600M Railway crossing works Supplying and fixing clear water pump sets 30 HP 2 Nos,25HP 2 Nos,20 HP 2 Nos ,10 HP 2 Nos |
| Status |
On-going |
| District |
Alappuzha |
| Executing Office |
KIIFB Projects (ALP) |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
207700000 |
| TS Number |
TS/2020-2021/2020/2802 |
| Technical specification |
Construction of 16 LL OHSR and 5 LL Sump at Chathanad in Alappuzha Municiplaity Construction of 16 LL OHSR and 3 LL Sump at Vadikadu in Alappuzha Municiplaity Construction of 12 LL OHSR and 3 LL Sump cum pump house at Kattoor in Mararikulam South Pt Construction of Operator Quarters Laying clear Water Pumping main Kulamakki to OHSR (R20) at FHC Kattoor – 280mm HDPE - 2600M Railway crossing works Supplying and fixing clear water pump sets 30 HP 2 Nos,25HP 2 Nos,20 HP 2 Nos ,10 HP 2 Nos |
| Contractor |
M/s Midland Engineering and contracting company (Mob: 6282209419) |
No project review have been added to this project
Reported Issues
| Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
| 25 Oct 2021 |
Pending |
Pending |
Contract Related Risks |
Push through between Kalavoor and Tumboli stations at sarvodayapuram in Mararikulam south Panchayat at Chainage between 49/100-49/200.Joint inspection conducted on 7/9/2021 |
No comments available. |
Pending |
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
26/02/2021 |
| Scheduled date of Completion as per agreement |
25 Feb 2023 |
| Expected date of Completion |
15/08/2025 |
Processing Dates
| TS Date |
12 Nov 2020 |
| Estimate Approval |
12 Nov 2020 |
| NIT Approval |
13 Nov 2020 |
| Tender Closing |
28 Nov 2020 |
| Technichal Pre-Qualification |
24 Dec 2020 |
| Price bid opening |
01 Dec 2020 |
Approval Dates
| Workorder Date |
12 Feb 2021 |
| NA |
26 Feb 2021 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Alappuzha KIIFB - AE 4 |
| Date: 27/04/2026 |
Work in progress | 96% Completed
Agmt no: 50/2020-21/SE/PHC/ALP Dt: 26/02/2021. Original TOC 25.02.2023. Time of completion extended up to 25.09.2024. Construction of 12LL OHSR at KATTOOR in Mararikkulam South Panchayath- Kattoor OHSR commissioned. Inaugurated on 03/02/2025. Railway caution sanction pending .Construction of 16LL OHSR at VADIKADU- Works completed. Construction of 16LL OHSR at CHATHANAD -completed. 600mm MS pipe -100m laying-interconnection works ( PWD road cutting sanction obtained on15.04.2025) to be started.Test pit taken on 04.05.2025 for pipe laying and Interconnection works at Triveni jn. Laying of clear water pumping main from Kulamakki to Kattoor OHSR - completed. Replacement of motor (2nos )& MS work at Kulamakki pumphouse is completed . Pazhavangady -Construction of Staff Quarters- Completed. Some components for 100% finishing of these work still pending with the contractor, letter sent to contractor for providing this. 96% work completed..
| Alappuzha KIIFB - AE 4 |
| Date: 24/04/2026 |
Work in progress | 96% Completed
Agmt no: 50/2020-21/SE/PHC/ALP Dt: 26/02/2021. Original TOC 25.02.2023. Time of completion extended up to 25.09.2024. Construction of 12LL OHSR at KATTOOR in Mararikkulam South Panchayath- Kattoor OHSR commissioned. Inaugurated on 03/02/2025. Railway caution sanction pending .Construction of 16LL OHSR at VADIKADU- Works completed. Construction of 16LL OHSR at CHATHANAD -completed. 600mm MS pipe -100m laying-interconnection works ( PWD road cutting sanction obtained on15.04.2025) to be started.Test pit taken on 04.05.2025 for pipe laying and Interconnection works at Triveni jn. Laying of clear water pumping main from Kulamakki to Kattoor OHSR - completed. Replacement of motor (2nos )& MS work at Kulamakki pumphouse is completed . Pazhavangady -Construction of Staff Quarters- Completed. Some components for 100% finishing of these work still pending with the contractor, letter sent to contractor for providing this. 96% work completed..