- Home
- State plan-Mini WSS to Kodikunnu, Njando...
State plan-Mini WSS to Kodikunnu, Njandoorkonam Division in Thiruvananthapuram Corporation and Adjoining villages
Project |
State plan-Mini WSS to Kodikunnu, Njandoorkonam Division in Thiruvananthapuram Corporation and Adjoining villages |
Project Code |
TVMGOK07202431 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Mini WSS to Kodikunnu in Njandoorkonam Division Thiruvananthapuram’ for a total outlay of Rs.9.5 crores. |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum Project Dn |
AS Amount (Rs) |
95000000
|
AS Number |
G.O.(Rt)No.472/2020/WRD |
TS Amount (Rs) |
93100000 |
TS Number |
TS/2020-2021/17681 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
25000 |
Capacity in MLD |
0.35 |
Actual Project Completion Date |
20 Jan 2022 |
Coverage |
The work is to cater potable water to the njandoorkonam division and partly to the vembayam gramapanchayth- 3 wards |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
State plan-Mini WSS to Kodikunnu Njandoorkonam Division in Thiruvananthapuram Corporation and Adjoining villages |
Trivandrum Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 May 2024 |
No work @ site |
Thiruvananthapuram Project AE5 |
|
09 May 2024 |
No work @ site |
Thiruvananthapuram Project AE5 |
|
30 Apr 2024 |
No work @ site |
Thiruvananthapuram Project AE5 |
|
22 Apr 2024 |
No work @ site |
Thiruvananthapuram Project AE5 |
|
18 Apr 2024 |
No work @ site |
Thiruvananthapuram Project AE5 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
14/02/2021 |
Scheduled date of Completion of the Project |
20 Jan 2022 |
Expected date of Completion |
19/05/2022 |
Processing Dates
AS Date |
27 Jul 2020 |
TS Date |
22 Aug 2020 |