Supply and installation of capacitor

Project Supply and installation of capacitor
Project Code KNRGOK01229016P1
Type Package
Main Project Supply and installation of capacitor
Funding Agency GOK
Category MACE of RWSS
Type of scheme Water Supply
Scheme 4215-01-800-89
Description Power factor improvement in the KSEBL connection-mace of Kolachery water supply scheme supply and installation of super heavy duty Capacitor for 120 HP VT pump set at Intake well cum pump house Veliyambra
Status Completed
District Kannur
Executing Office Chavasseryparamba WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 30680
TS Number TS/2019-20/2019/11060
Technical specification full coverage to Koodali,Mundery,Kuttiattoor,Mayyil,Kolachery and Narath Panchayaths

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 09/02/2022
Scheduled date of Completion as per agreement 28 Feb 2022
Expected date of Completion 31/03/2022

Processing Dates

TS Date 01 Feb 2022
Estimate Approval 01 Feb 2022

Approval Dates

Workorder Date 09 Feb 2022
NA 10 Feb 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chavasseryparamba WS Sn AE
Date: 18/04/2022

Work has been completed | 100% Completed

Bill Submitted.

Chavasseryparamba WS Sn AE
Date: 08/04/2022

Work has been completed | 100% Completed

Capacitor supplied by the contractor Installation work completed.Bill under preparation.