AMRUT-02 - WSS TO KOYILANDY MUNICIPALITY-PROVIDING FUNCTIONAL HOUSE HOLD TAP CONNECTION IN VARIOUS WARDS-Pipeline Work

Project AMRUT-02 - WSS TO KOYILANDY MUNICIPALITY-PROVIDING FUNCTIONAL HOUSE HOLD TAP CONNECTION IN VARIOUS WARDS-Pipeline Work
Project Code CLTAMRUT022315391
Type Main project
Funding Agency AMRUT
Category AMRUT 2
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-02 - WSS TO KOYILANDY MUNICIPALITY-PROVIDING FUNCTIONAL HOUSE HOLD TAP CONNECTION IN VARIOUS WARDS-Pipeline Work
Status On-going
District Kozhikkode
Executing Office Vadakara PH Dn
AS Amount (Rs) 227940000
AS Number G.O.(Rt)No.473/2023/LSGD
TS Amount (Rs) 217400000
TS Number WRD/KWA-CE(NR)/EST_TS/5274/2022_26_1_1
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted
Capacity in MLD 174.00
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 AMRUT-02 - WSS TO KOYILANDY MUNICIPALITY-PROVIDING FUNCTIONAL HOUSE HOLD TAP CONNECTION IN VARIOUS WARDS-Pipeline Work Kozhikode Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Feb 2024 Work order issued on 21.09.2023, Agreement executed on 19.10.2023, Site hand over on 29.10.2023. Kozhikode Project Dn AE5
04 Jan 2024 Work order issued on 21.09.2023, Agreement executed on 19.10.2023, Site hand over on 29.10.2023. Kozhikode Project Dn AE5
26 Dec 2023 Work order issued on 21.09.2023, Agreement executed on 19.10.2023, Site hand over on 29.10.2023. Kozhikode Project Dn AE5
14 Dec 2023 Work order issued on 21.09.2023, Agreement executed on 19.10.2023, Site hand over on 29.10.2023. Kozhikode Project Dn AE5
01 Dec 2023 Work order issued on 21.09.2023, Agreement executed on 19.10.2023, Site hand over on 29.10.2023. Kozhikode Project Dn AE5

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 29/10/2023
Scheduled date of Completion of the Project 28 Oct 2024
Expected date of Completion 28/10/2024

Processing Dates

AS Date 23 Feb 2023
TS Date 31 May 2023

Other details